Performance Verification
4
N2795/6A User’s Guide
41
12
Perform a Calibration for the
PORT 1
side of the Reference plane.
a
Press the
reflection
screen key.
b
Connect the open end of 85052D Calibration Standard
to the
non-pincher side of the PV/DS test board.
c
Select the
open
screen key under the
Forward
group.
d
Wait until the VNA beeps indicating that it has completed the
task.
e
Connect short end of Calibration Standard to the
non-pincher side of the PV/DS test board.
f
Select
short
screen key under the
Forward
group.
g
Wait until the VNA beeps indicating that it has completed the
task.
h
Connect load end of Calibration Standard to the non-pincher
side of the PV/DS test board.
i
Select the
loads
screen key under the
Forward
group.
j
Press
broadband
screen key selection.
k
Wait until the VNA beeps indicating that it has completed the
task.
l
Press the
done loads
screen key.
m
You have just calibrated one side of the reference plane.
13
Connect the other high quality SMA cable to the VNA’s
PORT 2
.
Summary of Contents for N2795A
Page 4: ...4 N2795 6A User s Guide Contents...
Page 29: ...Characteristics and Specifications 2 N2795 6A User s Guide 29 Dimensions...
Page 30: ...30 N2795 6A User s Guide 2 Characteristics and Specifications...
Page 34: ...34 N2795 6A User s Guide 3 Performance Data Plots...
Page 48: ...48 N2795 6A User s Guide 4 Performance Verification...