6 Verify Operation
S9106AC-2IF, -4UP, and -42D 5G FR1 Multi-port Transceiver Solutions, Startup Guide
55
After connecting AC power cords and powering on equipment, the
following process must be repeated for each M9410A PXIe VXT
Vector Transceiver and its selected X-Apps software pair in the
system; the S9106AC-2IF 5G FR1 Multi-port Transceiver contains
two M9410A PXIe VXTs that are labelled on the
Rugged Front Panel as Transceiver 1 and Transceiver 2.
6. 1. 2 Verify X-Apps Controls S9106AC-2IF RF Ports at 3 GHz
This process verifies operation of
RF Transceiver .380 - 6 GHz
,
RF Out
➀
and
RF In
➁
located on the Rugged Front Panel.
1. On RF Transceiver 1, connect an RF loop-back cable from
RF Out
➀
to
RF In
➁
located on the Rugged Front Panel.
This loop-back cable is not included with the
S9106AC-2IF 5G FR1 Multi-port Transceiver.
Use a cable with two adapters (or equivalent) such as:
one 5063-1530 RF Cable, SMA (m) to SMA (m), 152.4 mm (6.0 in) and
two 1250-1250 Adapters, SMA (f) to Type-N (m)
Summary of Contents for S9106AC-2IF
Page 6: ...2 S9106AC 2IF 4UP and 42D 5G FR1 Multi port Transceiver Solutions Startup Guide ...
Page 24: ...20 S9106AC 2IF 4UP and 42D 5G FR1 Multi port Transceiver Solutions Startup Guide ...
Page 42: ...38 S9106AC 2IF 4UP and 42D 5G FR1 Multi port Transceiver Solutions Startup Guide ...
Page 56: ...52 S9106AC 2IF 4UP and 42D 5G FR1 Multi port Transceiver Solutions Startup Guide ...