Keyscan Inc. A Member of the Kaba Group
14
Steps to Program and Install a NETCOM2P/ACU Control Board …cont’d
20.
Connect an Ethernet cable from a network jack to the RJ45 terminal on the
NETCOM2P.
21.
Enable M1 for communication with the NETCOM2P as follows:
J16 – pin F = ON / pin G = OFF
S2 – switch 7 = ON / switch 8 = OFF
22.
Momentarily place a jumper on J6 Reset or press the S1 switch on the control board.
23.
At the PC/laptop, click on the OK button in the Disconnect the serial cable… screen.
24.
If the PC/laptop has a network connection, verify network communication with the
NETCOM2P. Select the Start PING button on the Keyscan NETCOM Utility screen.
If the PC/laptop does not have a network connection, close the NETCOM Program
Tool utility, complete any remaining connections for permanent operation, re-
locate to a PC connected to the network and PING the NETCOM2’s IP address
using the Command Prompt. The Average Round Trip Times should be less than
100 milliseconds and the Packets Sent should equal the Packets Received with
0% loss. Continue at step 26.
25.
Wait for the PING Status result message:
IP Success indicates the NETCOM2P has network communication
IP Timed Out indicates the NETCOM2P does not have network communication—
verify settings and connections
26.
Click on the x in the upper right corner of the Keyscan NETCOM Utility screen to close
the application.
27.
Disconnect the power from the ACU control board.
28.
Re-mount the ACU protective cover.
29.
Re-apply power after the ACU protective cover has been re-mounted.
30.
On the control board, do one of the following steps depending on the PC109x control
board version:
J16 Jumpers - Place a jumper on J16—pin H. Momentarily place a jumper on J1
to re-load the factory default settings. This may take two minutes. Do not make
any changes to the control board while the system status LED is flashing red and
the piezo is beeping. When completed, remove the jumper from J16—pin H.
S1 and S3 Switches – After applying power, press S1, wait 5 seconds, and then
press S3 within 10 seconds to load the factory defaults. Allow approximately 2
minutes and do not make any changes to the control board while the system
status LED is flashing red and the piezo is beeping.
31.
Close and secure the ACU enclosure door.
32.
Depending on the type of installation do one of the following steps:
If this is a new installation, install the Keyscan software, set up the site, and
perform a full panel upload.
If this is an existing installation, log on to a Client software module, edit the site
setup screens and perform a panel upload.