7.
Enter the
HA Shared address
. Click
Set Shared address
.
8.
Enter the
HA Partner IP address
. Click
Set Partner address
.
9.
Click
Reboot Now
.
10.
Wait 45 to 60 seconds, then click
Continue
.
11.
Wait until the HA icons at the top of the screen are green.
12.
If not yet done, connect the LoadMaster to the Real Server network and the open
network side.
13.
In the main menu, select
Local Administration > System Reboot
.
Figure 7-3: Reboot
14.
Click
Reboot
.
15.
Click
OK
.
16.
Click
Continue
.
It is optional, but KEMP recommends simulating a failover to the newly restored partner to
check that everything is working OK. There are two ways to do this, both are detailed in the
sections below.
7.2.1
Reboot the Active Unit
Rebooting the active unit should cause the new unit to take over. To do this, follow the steps
below in the WUI of the active unit:
1.
In the main menu of the WUI, select
Local Administration > System Reboot
.
Figure 7-4: Reboot
2.
Click
Reboot
.
3.
Wait 45 to 60 seconds, then click
Continue
.