Section 2: S540 site preparation and installation
S540 Power Semiconductor Test System Administrative Guide
2-30
S540-924-01 Rev. D / January 2019
1.
Position the cabinet where needed on a smooth, level floor.
2.
Place the floor mounting brackets at the corners and make sure you have enough room for
proper placement.
3.
To properly place the mounting brackets, lift the cabinet by the leveling legs.
Lifting the cabinet allows the holes in the mounting brackets to line up with the holes in the lower
frame of the cabinet.
4.
Temporarily attach the mounting brackets to each corner with the provided screws.
The following figure shows the restraint brackets and bolt installation for the system cabinet.
Figure 33: S540 seismic restraints
5.
Mark the position of the mounting holes to the floor with a marker.
6.
Remove the mounting brackets and also mark the location of the cabinet leveling legs.
7.
Lower the cabinet and move as needed for drilling and installing the customer-supplied floor
anchors.