background image

Model 4299-3 Installation Instructions 

  

 

 

PA-942 Rev. A / May 2007

 

Installation 

The following procedure outlines the installation of the rack mount kit. 

WARNING  

Make sure the instrument that is being installed is in a powered down state with all 
cables unplugged. Failure to install an instrument in a  discharged state may cause an 
electrical shock or death.
 

CAUTION

 • 

Place the hottest equipment (for example, the power supply), at the top of 

 the 

rack 

 • 

Place precision equipment  as low as possible in the rack (where 

 

temperatures are cooler) 

 • 

Follow instructions included with Keithley equipment for rack mounting. 

NOTE  

1U is a standard vertical spacing and is equal to 1.75 inches. Typical  
distance between the mounting holes on rack rails is 0.125” (1/8”).  

Step 1. Prepare instrument 

To prepare the instrument for mounting, remove the handle, the mounting ears, and both rear feet. The following 

information outlines this process. 

1.  

Remove the handle

 —The handle serves as an adjustable tilt-bail. Adjust its position by gently pulling it 

away from the sides of the instrument case and swinging it up or down. To remove the handle, swing the 

handle below the bottom surface of the case and back until the orientation arrows on the handles line up 

with the orientation arrows on the mounting ears (refer to Figure 1). With the arrows lined up, pull the ends 

of the handle away from the case. 

2.  

Remove mounting ears.

 

•   Remove the screw that secures each mounting ear.  

•   Pull down and out to remove each ear. 

 