7.1
Connection overview
Fig. 7-6: 3-phase connection overview
1
... Power connection (power grid)
2
... Pre-meter fuses
3
... Energy meter of the power supply
company (PSC)
4
... Post-meter fuses
5
... Split-core current transformer
6
... KC-E10
7
... 16 A Type B fuses
8
... Consumer
In 1-phase operation, the split-core current transformers and voltage input
are to be connected to the device for phase L1. At least phase (phase con-
ductor) L1 and neutral conductor N must be connected, since they supply
the device with power.
Summary of Contents for KeContact E10
Page 1: ...KeContact E10 Energy meter Installation manual V 1 00 Original instructions...
Page 30: ...E10 Declaration of conformity V1 00 30 KEBA 2023 15 Declaration of conformity...
Page 31: ...E10 Declaration of conformity V1 00 31 KEBA 2023...
Page 33: ......
Page 34: ...KEBA Energy Automation GmbH Reindlstra e 51 4040 Linz Austria www keba com...