Pre-commissioning checks

Before initial commissioning, check whether all the necessary conditions have been met so that
the unit can operate safely and properly.

Electrical tests

Check whether all lines have been properly laid.

Check whether all lines have the necessary cross-section.

Are all wires connected in accordance with the electric wiring diagrams?

Is the earth wire connected and wired throughout?

Check all external electrical connections and terminal connections are fixed in place and
tighten if necessary.