Pre-commissioning checks
Check before initial commissioning whether all necessary conditions have been met so that the unit can function safely and
properly.
Structural tests
Check that the unit is securely standing and fixed.
Check the horizontal installation/suspension of the unit.
Check whether all components are properly fitted.
Check whether all dirt, such as packaging or site dirt, has been removed.
Electrical tests
Check whether all lines have been properly laid.
Check whether all lines have the necessary cross-section.
Are all wires connected in accordance with the electric wiring diagrams?
Is the earth wire connected and wired throughout?
Check all external electrical connections and terminal connections are fixed in place and tighten if necessary.
Check whether DIP switches have been correctly set in accordance with the wiring diagram.
Water-side checks
Check whether all supply and drainage lines have been properly connected.
Fill pipes and unit with water and bleed.
Check whether all bleed screws are closed.
Check leak tightness (pressure test and visual inspection).
Check whether the parts carrying water have been flushed through.
Check whether any shut-off valves fitted on site are open.
Check whether any electrically actuated shut-off valves have been properly connected.
Check whether all valves and actuators are working properly (note permitted mounting position).
Air-side checks
Check whether there is unimpeded flow at the air inlet and outlet.
Once all checks have been completed, initial commissioning can be carried out in line with
.
Summary of Contents for Katherm QL 300
Page 2: ......
Page 16: ...Katherm QL Assembly installation and operating instructions 16 Overall length...
Page 17: ...Katherm QL Assembly installation and operating instructions 17...
Page 18: ...Katherm QL Assembly installation and operating instructions 18...
Page 36: ...Katherm QL Assembly installation and operating instructions 36 12 Certificates...