Description of battery charger

1

Technical description

The SLT 100 battery charger is designed
for the fully automatic charging and
recharging of lead batteries and is
equipped with a special electronic charging
system (1, 2). The rated charging current
specified flows at a charging voltage of
2.0 volts per cell. The battery must be
assigned so that the initial charging current
is approx. 16 Amperes per 100 Ah of
battery capacity.

The difference lies in the initial charging
current – see data plate (3).

Initial charging voltage:  24, 48, 80 volt

depending on type 

Initial charging current:  20 A-160 A,  

depending on type

The battery charger is protected on the
secondary side by a fuse (5) acting as
a short circuit protection and by a sensor to
limit the transformer temperature.

To ensure the operational safety of the
system, only self-cooled stacked silicon
rectifier elements (4) are used. 

Stray field transformers (6) are used to
comply with the specified charging
characteristic.
The stray field transformers are equipped
with additional primary tapping to
DIN 41 774,  corresponding  to  +10 %,
+5 %,  0 %  and  -5 %  to  allow  for  mains
voltage deviations.

Z

Modifications should only be carried out by
the manufacturer’s service department.

2

3

1

4

5

6

SLT 100

SLT 100

 15

11

15.GB

5

Commissioning

Z

For transport and assembly see chapter C
on page 5.
For chargers with electrolyte circulation the
air volume flow must also be adapted to the
battery, see "Air volume flow presetting” on
page 15.

5.1

Air volume flow presetting

Switch (3) has the following factory settings
for all SLT 100 large battery chargers:

6

Maintenance of the filter

The blue suction filter (5) on the bottom of
the pump must be checked for soiling at
regular intervals. 

In strongly dusty areas, it is to be replaced
every 3 months, otherwise at least every 6
months.
To replace the suction filter (5) tip the blue
insertion sleeve to the side and replace the
polishing cotton.

Figure: Large battery charger

Figure: Small battery charger

Voltage class 

in V

Volume in l/min

24

4

48

8

80

12

Item

Description

4

Cable to the charging switch

5

Filter

6

Air hose

4

5

6

6

5

4

Summary of Contents for SLT 100

Page 1: ...SLT 100 SLT 100 Operating instructions 50451882 SLT 100 G 10 04 11 15...

Page 2: ...k should therefore be assumed from the present operating instructions Safety instructions and important explanations are indicated by the following graphics F Used before safety instructions which mus...

Page 3: ...9 3 5 Fault indication safety cut out 9 3 6 Manual charging interruption 10 3 7 Boosting charge 10 3 8 Manual Compensation Charge 10 3 9 Automatic equilising charge function 10 4 Charging state indica...

Page 4: ...I2 0709 GB...

Page 5: ...or climb onto it Additional components may only be installed after a written approval by the manufacturer has been obtained User obligations User within the meaning of these operating instructions is...

Page 6: ...ing voltage 24 48 80 volt depending on type Initial charging current 20 A 160 A depending on type The battery charger is protected on the secondary side by a fuse 5 acting as a short circuit protectio...

Page 7: ...equipment may only be carried out by skilled electricians Z To attach additional external equipment contact the manufacturer s service department Charging curve pulse charging T1 Battery gassing phase...

Page 8: ...perature is in the permissible range again charging will be continued and the LED goes off Optimum battery charging requires adaptation to the mains supply The charging electronics are zero voltage pr...

Page 9: ...m the transport pallet Z This does not apply to pallets on which the battery charger is permanently mounted These pallets have a fireproof base Packaging material is to be disposed of correctly Z In a...

Page 10: ...harging batteries leads to the generation of explosive gases Sufficient ventilation must be provided during charging and at least for one hour after charging has been completed The room must be ventil...

Page 11: ...re correct operation of the battery charger and especially correct functioning of automatic charging switches and measurement instrument display At the start of charging the amperage and voltage must...

Page 12: ...Flashing pulses Meaning 2 Incorrect battery voltage 3 Safety charge exceeded Main charging time or recharging time in case of pulse charging 4 Excess temperature 5 Mains failure is only indicated when...

Page 13: ...ch and store the position of the charging program All LED displays go out When the mains supply is restored the LEDs display the previous condition The battery charge continues The stored charging ind...

Page 14: ...ces between the individual cells When the compensation charge is complete the recharging time is increased on a single occasion by 2 hours When you press the control key 3 for 10 sec prior to connecti...

Page 15: ...ce and repair of SLT 100 chargers must only be carried out by qualified personnel The manufacturer s service department has field technicians specially trained for these tasks 3 Cleaning operations F...

Page 16: ...contactors 18 Secondary F1 fuse 3 electrolyte circulation pump Aquamatik o F3 fuse 17 D400V devices without neutral conductor F12 fuse 19 M Version and rated value of the fuses must not be changed Ref...

Page 17: ...charged F It is forbidden to store food in the vicinity of battery chargers Z The VDE 0510 safety regulations must be observed 3 Electrolyte circulation EUW During charging the electrolyte circulatio...

Page 18: ...m is working correctly and the recharging time is reduced the green LED 1 is lit on the control board Z A defective hose system can be identified via the air pressure monitor Service message flashes 4...

Page 19: ...hargers 6 Maintenance of the filter The blue suction filter 5 on the bottom of the pump must be checked for soiling at regular intervals In strongly dusty areas it is to be replaced every 3 months oth...

Page 20: ...Charging time is not reduced Possible causes The hose system is defective see Air pressure monitor on page 14 Filter 5 is clogged Elimination measures Replace the hose system Replace filter 5 7 3 Malf...

Page 21: ...harges The curves for the individual charges can be viewed on a PC The necessary software is supplied on a CD with the charge information system Z For information on operating the charge information s...

Page 22: ...e data plate 1 2 4 5 9 8 3 6 7 10 11 Item Designation Item Designation 1 Series 7 No of cells type 2 Type 8 Protection class 3 Serial No 9 Output 4 Year of manufacture 10 Battery capacity 5 Fuse 11 Ma...

Page 23: ......

Page 24: ......

Reviews: