© 2022 Johnson Level & Tool — 24
EXAMPLES
COMPLEX CONCRETE VOLUME
You’re going to pour an odd-shaped patio 3-3/4 Inches
deep with the dimensions shown below . First, calculate
the total Area (by dividing the drawing into three
individual rectangles) and then determine the total Yards
of concrete required for this job .
25'-0"
20'-6"
4'-2"
9'-6"
8'-6"
9'-0"