INSPECTION

As soon as a unit is received, it should be inspected for possible dam-
age  during  transit.  If  damage  is  evident,  the  extent  of  the  damage
should  be  noted  on  the  carrier’s  freight  bill.  A  separate  request  for
inspection by the carrier’s agent should be made in writing. Also, before
installation, the unit should be checked for screws or bolts which may
have  loosened  in  transit.  There  are  no  shipping  or  spacer  brackets
which need to be removed from the interior of this unit.

FURNACE LOCATION AND CLEARANCES

The furnace shall be located using the following guidelines:

1. Where a minimum amount of air intake/vent piping and elbows will

be required.

2. As centralized with the air distribution as possible.
3. Where adequate combustion air will be available (particularly when

the appliance is not using outdoor combustion air).

4. Where it will not interfere with proper air circulation in the confined

space.

5. Where  the  outdoor  vent  terminal  will  not  be  blocked  or  restricted.

Refer to “VENT CLEARANCES” located in SECTION VII of these
instructions. These minimum clearances must be maintained in the
installation.

6. Where the unit will be installed in a level position with no more than

1/4” (6.4 mm) slope side-to-side and front-to-back to provide proper
condensate drainage.

Installation in freezing temperatures:

1. Furnace shall be installed in an area where ventilation facilities pro-

vide for safe limits of ambient temperature under normal operating
conditions. Ambient  temperatures  must  not  fall  below  32°F  (0°C)
unless the condensate system is protected from freezing. 

2. Do  not  allow  return  air  temperature  to  be  below  55ºF  (13°C)  for

extended periods. To do so may cause condensation to occur in the
main heat exchanger, leading to premature heat exchanger failure.

3. If  this  furnace  is  installed  in  an  unconditioned  space  and  an

extended power failure occurs, there will be potential damage to the
internal  components.  Following  a  power  failure  situation,  do  not
operate the unit until inspection and repairs are performed.

Clearances for access/service:

Ample clearances should be provided to permit easy access to the unit.
The following minimum clearances are recommended:
1. Twenty-four  (24)  inches  (61  cm)  between  the  front  of  the  furnace

and an adjacent wall or another appliance, when access is required
for servicing and cleaning.

2. Eighteen (18) inches (46 cm) at the side where access is required

for passage to the front when servicing or for inspection or replace-
ment of flue/vent connections.

In all cases, accessibility clearances shall take precedence over clear-
ances  for  combustible  materials  where  accessibility  clearances  are
greater.

Installation in a residential garage:

A  gas-fired  furnace  for  installation  in  a  residential  garage  must  be
installed so the burner(s) and the ignition source are located  not less
than 18” (46 cm) above the floor, and the furnace must be located or
protected to avoid physical damage by vehicles.

*  24" clearance in front and 18" on side recommended for service access.
All furnaces approved for alcove and attic installation.

FOR FURNACES INSTALLED IN THE COMMON-

WEALTH OF MASSACHUSETTS ONLY

For all side wall horizontally vented gas fueled equipment installed in
every dwelling, building or structure used in whole or in part for resi-
dential  purposes,  including  those  owned  or  operated  by  the  Com-
monwealth and where the side wall exhaust vent termination is less
than seven (7) feet above finished grade in the area of the venting,
including but not limited to decks and porches, the following require-
ments shall be satisfied:
1.

INSTALLATION  OF  CARBON  MONOXIDE  DETECTORS. 

At

the  time  of  installation  of  the  side  wall  horizontal  vented  gas
fueled  equipment,  the  installing  plumber  or  gasfitter  shall
observe  that  a  hard  wired  carbon  monoxide  detector  with  an
alarm and battery back-up is installed on the floor level where the
gas  equipment  is  to  be  installed.  In  addition,  the  installing
plumber or gasfitter shall observe that a battery operated or hard
wired  carbon  monoxide  detector  with  an  alarm  is  installed  on
each additional level of the dwelling, building or structure served
by the side wall horizontal vented gas fueled equipment. It shall
be the responsibility of the property owner to secure the services
of  qualified  licensed  professionals  for  the  installation  of  hard
wired carbon monoxide detectors

a.

In  the  event  that  the  side  wall  horizontally  vented  gas
fueled equipment is installed in a crawl space or an attic,
the  hard  wired  carbon  monoxide  detector  with  alarm  and
battery back-up may be installed on the next adjacent floor
level.

b.

In the event that the requirements of this subdivision can
not  be  met  at  the  time  of  completion  of  installation,  the
owner shall have a period of thirty (30) days to comply with
the  above  requirements;  provided,  however,  that  during
said thirty (30) day period, a battery operated carbon mon-
oxide detector with an alarm shall be installed.

2.

APPROVED CARBON MONOXIDE DETECTORS. 

Each carbon

monoxide detector as required in accordance with the above pro-
visions shall comply with NFPA 720 and be ANSI/UL 2034 listed
and IAS certified.

3.

SIGNAGE. 

A metal or plastic identification plate shall be perma-

nently  mounted  to  the  exterior  of  the  building  at  a  minimum
height  of  eight  (8)  feet  above  grade  directly  in  line  with  the
exhaust vent terminal for the horizontally vented gas fueled heat-
ing appliance or equipment. The sign shall read, in print size no
less  than  one-half  (1/2)  inch  in  size,  “GAS

  VENT  DIRECTLY

BELOW. KEEP CLEAR OF ALL OBSTRUCTIONS”

.

4.

INSPECTION. 

The state  or  local  gas inspector  of  the  side wall

horizontally vented gas fueled equipment shall not approve the
installation unless, upon inspection, the inspector observes car-
bon  monoxide  detectors  and  signage  installed  in  accordance
with the provisions of 248 CMR 5.08(2)(a)1 through 4.

 WARNING

Improper installation in an ambient below 32ºF (0.0° C) could create a
hazard, resulting in damage, injury or death.

 WARNING

Liquid anti-freeze will cause damage to internal plastic parts of this
furnace.  DO NOT attempt to winterize the furnace using liquid
anti-freeze.

Table 1: 

Unit Clearances to Combustibles

Application

Upflow

Downflow

Horizontal

Top

1" 

0" 

0" 

Vent

0" 

0" 

0" 

Rear

0" 

0" 

0" 

Side

0" 

0" 

1" 

Front*

0" 

0" 

0" 

Floor

Combustible

Combustible

1

1. For combustible floors only when used with special sub-base.

Combustible

Closet

Yes

Yes

Yes

Line Contact

No

No

Yes

!

!

Summary of Contents for TM9E

Page 1: ... Vent Termination 24 Downward Venting 24 Direct Vent Air Intake Connection and Vent Connection 24 Combustion Airflow Path Through The Furnace Casing 25 Ambient Combustion Air 26 Attic and Crawl Space Combustion Air Termination 27 Gas Valve 30 Reading Gas Pressure 30 Furnace Control Board 31 Wiring Diagram 36 LIST OF TABLES Unit Clearances to Combustibles 4 Cabinet and Duct Dimensions 8 Recommended...

Page 2: ... temperature rise and venting according to the manufacturer s instructions 10 When installed in a non HUD Approved Modular Home or building constructed on site combustion air shall not be supplied from occu pied spaces 11 The size of the unit should be based on an acceptable heat loss calculation for the structure ACCA Manual J or other approved methods may be used 12 When moving or handling this ...

Page 3: ...sdiction In the United States and Canada follow all codes and standards for the following using the latest edition available STEP 1 Safety US National Fuel Gas Code NFGC NFPA 54 ANSI Z223 1 and the Installation Standards Warm Air Heating and Air Conditioning Systems ANSI NFPA 90B CANADA CAN CGA B149 1 National Standard of Canada Natu ral Gas and Propane Installation Codes NSCNGPIC STEP 2 General I...

Page 4: ...URNACES INSTALLED IN THE COMMON WEALTH OF MASSACHUSETTS ONLY For all side wall horizontally vented gas fueled equipment installed in every dwelling building or structure used in whole or in part for resi dential purposes including those owned or operated by the Com monwealth and where the side wall exhaust vent termination is less than seven 7 feet above finished grade in the area of the venting i...

Page 5: ...s cover shall be attached in such a manner as to prevent leaks DUCT FLANGES Four flanges are provided to attach ductwork to the furnace These flanges are rotated down for shipment In order to use the flanges remove the screw holding an individual flange rotate the flange so it is in the upward position and reinstall the screw then repeat this for all 4 flanges If the flanges are not used they must...

Page 6: ...tom opening However if the furnace is to be installed on a surface that is uneven or if it is to be installed on blocks or otherwise raised off the floor it will be necessary to seal the edges of the bottom panel to the casing using tape or other appropriate gasket material to prevent air leakage BOTTOM RETURN AND ATTIC INSTALLATIONS Bottom return applications normally pull return air through a ba...

Page 7: ...rt located approximately in the center of the furnace near the blower shelf and the third support should be at the return end of the fur nace Maintain a 6 15 2 cm minimum clearance between the front of the furnace and the support rods or straps All six suspension points must be level to ensure proper and quiet fur nace operation When suspending the furnace use a secure platform constructed of plyw...

Page 8: ... 2XWOHW 9HQW RQQHFWLRQ 2XWOHW 9HQW RQQHFWLRQ 2XWOHW Table 2 Cabinet and Duct Dimensions BTUH kW Input Nominal CFM m3 min Cabinet Size Cabinet Dimensions Illustrated in Figure 13 Approximate Operating Weights A in A cm B in B cm C in C cm Lbs kg 40 11 7 1000 28 3 A 14 1 2 36 8 13 3 8 34 0 11 3 4 29 8 113 60 17 6 1200 34 0 B 17 1 2 44 4 16 3 8 41 6 13 1 4 33 7 122 80 23 4 1200 34 0 B 17 1 2 44 4 16 ...

Page 9: ... Refer to Figure 11 For left side supply gas pipe arrangement two 1 2 elbows and two 1 2 x 1 1 2 pipe nipples must be used The arrangement shown in Figure 11 aligns entrance hole in furnace casing with supply gas pipe Furnace casing does not support installations completed using street elbows DANGER An overpressure protection device such as a pressure regulator must be installed in the gas piping ...

Page 10: ...ced on the octagon hub located on the gas inlet side of the valve Placing a wrench to the body of the gas valve will damage the valve causing improper opera tion and or the valve to leak Table 4 Nominal Manifold Pressure High Fire Gas Heating Value BTU cu ft Manifold Pressures Gas Heating Value MJ cu m Manifold Pressures Altitude feet Altitude m 0 7999 8000 8999 9000 9999 0 2437 2438 2742 2743 304...

Page 11: ...he main electrical source disconnected connect the thermostat wiring from the wiring connections on the thermostat to the terminal board on the ignition module as shown in Figures 13 14 Electronic thermostats require the common wire to be connected Apply strain relief to thermostat wires passing through cabinet If air conditioning equipment is installed use thermostat wiring to connect the Y and C...

Page 12: ...SUHVVRU XOO 6WDJH HDW LUVW 6WDJH RPSUHVVRU 7 50267 7 WHUQDO XPLGLVWDW 2SWLRQDO 2SHQ RQ XPLGLW 5LVH 9 XPLGL HU 2SWLRQDO FIGURE 15 Thermostat Chart 1H 2C Single Stage Furnace STD ECM Single Stage Air Conditioner 7KHUPRVWDW 6LQJOH 6WDJH XUQDFH 67 0 7ZR 6WDJH LU RQGLWLRQHU LUVW 6WDJH RPSUHVVRU RU 2 5HYHUVLQJ 9DOYH DQ 6HFRQG 6WDJH RPSUHVVRU 5 9ROW RW LUVW 6WDJH HDW 9ROW RPPRQ 9ROW RPPRQ 5 9ROW RW 6HFRQ...

Page 13: ...ll flow to the drain better if an open stand pipe is installed in the drain line See Figure 15 If indoor coil or humidifier drains are combined with the furnace drain then the open stand pipe could be raised higher above the 5 minimum Do not drain other devices humidifier indoor coil etc into the top opening of the vent stand pipe Instead install a second tee in the vented drain tube below the fur...

Page 14: ...d the bird screen cannot be installed This is only approved for upflow and horizontal applications when the intake pipe is located on the top of the furnace This is true for all long horizontal venting in any furnace configuration This will keep condensate from entering the furnace WARNING DO NOT terminate the condensate drain in a chimney or where the drain line may freeze If the drain line will ...

Page 15: ...ff so that no sagging loops will collect and hold condensate which will cause the furnace to not operate Shorten pressure switch hose Re route and shorten pressure switch hose Shorten rain gutter hose Move rain gutter hose to this position For 100 120 input furnaces the condensate drain is plumbed toward the left casing outlet from the factory For 040 060 080K input furnaces the condensate drain i...

Page 16: ...witch hose to this position NOTE May require the longer hose that is provided with wider cabinets Move condensate drain hose to this position May exit either side of the cabinet Move rain gutter hose to this position When drain hose routing changes are required be sure to cap all un used openings If rerouting hoses excess length should be cut off so that no sagging loops will collect and hold cond...

Page 17: ...ch hose to this position NOTE May require the longer hose that is provided with wider cabinets Change condensate drain connection to the 90 fitting provided Move condensate drain hose to this position Move rain gutter hose to this position NOTE May require hose extension that is provided with wider cabinets Move condensate drain hose to this position Change condensa drain connection to the 90 fitt...

Page 18: ...itting provided Move condensate drain hose to this position Move rain gutter hose to this position Change condensate drain connection to the 90 fitting provided Move condensate drain hose to this position AIRFLOW Move pressure switch hose to this position When drain hose routing changes are required be sure to cap all un used openings If rerouting hoses excess length should be cut off so that no s...

Page 19: ...e combustion air pipe 6 All models are supplied with 2 5 1 cm vent connections When the pipe must be increased to 3 7 6 cm diameter the transition from 2 to 3 must be done as close to the furnace as possible The 2 to 3 increase should be installed in the vertical position as to not create an area that will pool water 7 In Canada vents shall be certified to ULC S636 Standard for Type BH Gas Venting...

Page 20: ...45 80 000 4 125 100 000 2 20 100 000 2 NA 100 000 3 80 100 000 3 60 100 000 4 145 100 000 4 125 120 000 3 80 120 000 3 60 120 000 4 145 120 000 4 125 Elevation 4001 5000 Elevation 8001 9000 Model Input BTUH Pipe Size in Max equivalent Length ft Model Input BTUH Pipe Size in Max equivalent Length ft 40 000 2 50 40 000 2 30 40 000 3 75 40 000 3 55 40 000 4 140 40 000 4 120 60 000 2 50 60 000 2 30 60...

Page 21: ...PRESSURE SWITCHES REQUIRED FOR ALL INSTALLTIONS ABOVE 5000 FEET Part Number Models S1 1PS3302 100k 120k S1 1PS3306 60k S1 1PS3307 40k 80k FIGURE 21 Elbow Dimensions TABLE 8 Elbow Dimensions Elbow A Dimension Illustrated in Figure 25 2 Standard 2 5 16 3 Standard 3 1 16 2 Sweep 3 1 4 3 Sweep 4 1 16 TABLE 9 Equivalent Length of Fittings Fitting Equivalent Length 2 90 sweep elbow 5 feet of 2 pipe 2 45...

Page 22: ...1083163 UIM J 0918 22 Johnson Controls Unitary Products IMPORTANT The vent must be installed with the minimum required clearances and must comply with local codes and requirements ...

Page 23: ...rements of the gas supplier 12 30 5 cm or in accordance with local installation codes and the requirements of the gas supplier F Clearance to outside corner 12 30 5 cm or in accordance with local installation codes and the requirements of the gas supplier 12 30 5 cm or in accordance with local installation codes and the requirements of the gas supplier G Clearance to inside corner 3 feet 91 4 cm 3...

Page 24: ...h furnace must have a sepa rate vent pipe Under NO circumstances can the two vent pipes be tied together The combustion air side of the two pipe configuration shown in Figures 25 26 can be installed so the combustion air pipe terminates as described in outdoor combustion air or ventilated combustion air sec tions in these instructions Follow the instructions for outdoor combus tion air or ventilat...

Page 25: ...rmina tions Refer to Ambient Combustion Air Supply for proper installa tion Refer to Figure 29 3 VENTILATED COMBUSTION AIR Combustion air is supplied through a PVC or ABS pipe that is connected to the PVC coupling attached to the burner box and is terminated in a ventilated attic or crawl space The combustion air and the vent pipes are not termi nated in the same atmospheric zone Refer to Figure 3...

Page 26: ...able louvers are not permitted for use 4 A automatically operated damper or automatically adjustable lou vers shall be interlocked so that the main burner cannot operate unless either the damper or the louver is in the fully open position FIGURE 30 Combustion Airflow Path Through The Furnace Casing WARNING This type of installation requires that the supply air to the appliance s be of a sufficient...

Page 27: ...r 322 cm2 per 0 879 kW of the total input rating of all equipment located in the enclosure b Not less than the sum of all vent connectors in the confined space 3 The duct shall be least the same cross sectional area as the free area of the air supply inlet opening to which it connects 4 The blocking effects of louvers grilles and screens must be given consideration in calculating free area If the ...

Page 28: ...nd horizontal pitch Determine that there is no blockage restriction leakage corrosion or other deficiencies which could cause an unsafe condition 2 Close all building doors and windows and all doors 3 Turn on clothes dryers and TURN ON any exhaust fans such as range hoods and bathroom exhausts so they shall operate at maximum speed Open the fireplace dampers Do not operate a summer exhaust fan 4 F...

Page 29: ...other gas appliances and pilots 2 Run furnace for a minimum of 3 minutes in heating operation 3 Measure time in sec for gas meter to complete 1 revolution and note reading The 2 cubic feet dial provides a more accurate mea surement of gas flow 4 Refer to Table 14 for cubic feet of gas per hour 5 Multiply cubic feet per hour by heating valve BTU cu ft to obtain input If clocked rate does not match ...

Page 30: ...0 300 750 78 46 92 231 25 144 288 720 80 45 90 225 26 138 277 692 82 44 88 220 27 133 267 667 84 43 86 214 28 129 257 643 86 42 84 209 29 124 248 621 88 41 82 205 30 120 240 600 90 40 80 200 31 116 232 581 92 39 78 196 32 113 225 563 94 38 76 192 33 109 218 545 96 38 75 188 34 106 212 529 98 37 74 184 35 103 206 514 100 36 72 180 36 100 200 500 102 35 71 178 37 97 195 486 104 35 69 173 38 95 189 4...

Page 31: ...e operating instruc tions to place the unit back in operation 3 Adjust manifold pressure by adjusting gas valve regulator screw for the appropriate gas per the following 4 After the manifold pressure has been adjusted re calculate the fur nace input to make sure you have not exceeded the specified input on the rating plate Refer to CALCULATING THE FURNACE INPUT NATURAL GAS 5 Once the correct BTU k...

Page 32: ...ue gas sample for analysis it is permissible to drill a small hole in the plastic flue pipe for a sample probe provided that the vent piping is PVC and the hole is properly sealed afterwards If using a polypropylene vent system the vent sys tems manufacturer test port fitting must be used DO NOT drill a test port hole in polypropylene piping Use the following procedure 1 Drill a 11 32 hole in the ...

Page 33: ...High 1445 1423 1397 1365 1339 1311 1283 1250 1204 1140 Medium High 1282 1266 1232 1211 1182 1157 1128 1097 1069 1013 Medium 1098 1084 1059 1027 998 967 939 910 879 822 Medium Low 1012 993 953 930 894 851 828 773 752 692 Low 865 810 763 730 689 628 594 520 496 448 TM9E080C16MP11 High 1713 1682 1643 1600 1558 1519 1480 1436 1385 1333 Medium High 1554 1519 1485 1439 1404 1368 1327 1280 1176 1130 Medi...

Page 34: ...in the area surrounding burner exceeds its set point the gas valve is de energized The operation of this control indicates a malfunction in the combustion air blower heat exchanger or a blocked vent pipe con nection Corrective action is required These are manual reset controls that must be reset before operation can continue ...

Page 35: ...f and a retry operation begins Also if the flame is lost for 2 seconds during the 10 second stabilization period the gas valve is shut off and a retry operation begins During a retry operation the vent motor starts a 15 second inter purge and the ignitor warm up time is extended to 27 seconds If the flame is established for more than 10 seconds after ignition during a retry the control will clear ...

Page 36: ...former wires Both heating and cooling operations will be affected Check polarity at furnace and branch Check furnace grounding Check that flame probe is not shorted to chassis The furnace will not start the ignition sequence until this problem is corrected 10 RED FLASHES Gas valve energized with no call for heat The main blower and inducer blower will run and no ignition sequence will be started a...

Page 37: ...RING FERRULE 3 req d GASKET FOAM Door 1 5 ft req d GROMMET 3 req d HARNESS WIRING HOSE CONDENSATE HOSE RAIN GUTTER KNOB QUARTER TURN 4 req d MOTOR MOUNT ORIFICE BURNER Natural 45 PAN CONDENSATE PLUG SEAL 7 8 PLUG SEAL 2 3 8 PLUG VENT PIPE SIGHT GLASS OVAL 2 req d TUBING SILICON DESCRIPTION REPLACEMENT PART CONTACT INFORMATION This is a generic parts list To request a complete parts list refer to t...

Page 38: ...C LE SERVICE 1042427 UWD A 0413 Fault Code Retrieval To retrieve fault codes push and release ERROR button on control board The LED will flash the last five error codes beginning with the most recent If there are no fault codes in memory the LED will give two green flashes To clear the fault code memory push and hold the ERROR button for at least five seconds The LED will give three green flashes ...

Page 39: ...1083163 UIM J 0918 Johnson Controls Unitary Products 39 NOTES ...

Page 40: ...xhaust Size of 90 Degree Ells 0f 45 Degree Ells Length Length 0f 45 Degree Ells of 90 Degree Ells Polarity is correct black is L1 hot white is N neutral Ground wire is connected Line voltage value to furnace volts AC Low voltage value between R and C on furnace control board volts AC Thermostat Type Other System Equipment and Accessories Owner Information Equipment Data Furnace Configuration Conde...

Page 41: ...at exchanger cells Return Static in w c after filter furnace side Air Side Heating Air Side Cooling Air Side Continuous Fan Clean Up Give owner the owner s manual provided Gas Type Explain thermostat use and programming if applicable to owner Cycle Test Operate the furnace through several heating cycles from the thermostat noting and correcting any problems Operate the furnace through continuous f...

Reviews: