Johnson Controls TM8T*MP Installation Manual Download Page 7

521271-UIM-D-1211

Johnson Controls Unitary Products

7

CRITICAL COIL PROJECTION

The coil assembly must be located in the duct such that a minimum dis-
tance is maintained between the top of the coil and the top of the duct.
Refer to Table 2.

COIL / FURNACE ASSEMBLY - HC SERIES COILS

These coils are supplied ready to be installed in a right hand position or
a left hand position. When used in conjunction with a horizontal furnace
(blow through) application, the coil should be oriented with the opening
of the “A” coil closest to the furnace. See Figure 7.

DOWNFLOW DUCT CONNECTORS

All downflow installations must use a suitable duct connector approved
by the furnace manufacturer for use with this furnace. The duct connec-
tors are designed to be connected to the rectangular duct under the
floor and sealed. Refer to the instructions supplied with the duct con-
nector for proper installation. Refer to the separate accessory parts list
at the end of these instructions for the approved accessory duct con-
nectors.

RESIDENTIAL AND MODULAR HOME UPFLOW 

RETURN PLENUM CONNECTION

Return air may enter the furnace through the side(s) or bottom depend-
ing on the type of application. Return air may not be connected into the
rear panel of the unit.

SIDE RETURN APPLICATION

Side return applications pull return air through an opening cut in the 
side of the furnace casing. This furnace is supplied with a bottom block-
off panel that should be left in place if a side return is to be used. If the 
furnace is to be installed on a flat, solid surface, this bottom panel will 
provide an adequate seal to prevent air leakage through the unused 
bottom opening. However, if the furnace is to be installed on a surface 
that is uneven, or if it is to be installed on blocks or otherwise raised off 
the floor, 

it will be necessary to seal the edges of the bottom panel 

to the casing using tape or other appropriate gasket material to 
prevent air leakage.

BOTTOM RETURN AND ATTIC INSTALLATIONS

Bottom return applications normally pull return air through a base plat-
form or return air plenum. Be sure the return platform structure or return
air plenum is suitable to support the weight of the furnace.

The internal bottom panel must be removed for this application.

Attic installations must meet all minimum clearances to combustibles
and have floor support with required service accessibility.

DOWNFLOW APPLICATION

For downflow applications, the furnace must be turned upside-down so
that the circulating air enters at the top and exits the furnace at the bot-
tom. The combustion air inducer must be rotated 90° as shown in Fig-
ure 21. 

DO NOT BLOCK COMBUSTION AIR INLET OPENINGS.

HORIZONTAL APPLICATION

ATTIC INSTALLATION

Each coil is shipped with an external tie plate that should be used to
secure the coil to the furnace. It should be installed on the back side
of the coil using the dimpled pilot holes.

 See Figure 7.

 FIGURE 7:  

Horizontal Left or Right application (Right Shown)

 FIGURE 8:  

Combustible Floor Base Accessory

NOTICE

Use tie plate
supplied with coil

Air flow

Gas Furnace

FURNACE

WARM AIR PLENUM
WITH 1” FLANGES

FIBERGLASS
INSULATION

FIBERGLASS TAPE
UNDER FLANGE

COMBUSTIBLE FLOOR
BASE ACCESSORY

 FIGURE 9:  

Horizontal Application

This furnace may be installed in a horizontal position on either side
as shown above. It must not be installed on its back.

 FIGURE 10:  

Typical Attic Installation

Return
Air

Sediment

Trap

Gas Piping

Supply
Air

Vent (Maintain
required
clearances to
combustibles)

Line contact only permissible
between lines formed by the
intersection of furnace top
and two sides and building
joists, studs or framing

12”

30” MIN.
Work Area

Filter rack
must be a minimum
distance
of 18” (45.7 cm)
from the
furnace

12”

Sheet metal in
front of furnace
combustion air
Openings is
Recommended

Summary of Contents for TM8T*MP

Page 1: ...ressure 22 Blower Performance CFM Any Position CFM 24 These high efficiency compact units employ induced combustion reli able hot surface ignition and high heat transfer aluminized tubular heat exchan...

Page 2: ...binet support the ends of the furnace rather than lifting by the cabinet flanges at the return air openings bottom or sides or supply air opening 13 When lifting the furnace it is acceptable to use th...

Page 3: ...the National Fire Protection Association Inc Batterymarch Park Quincy MA 02269 or for only the NFGC contact the American Gas Association 400 N Capital N W Washington DC 20001 or www NFPA org CANADA NS...

Page 4: ...onoxide detector with an alarm and battery back up is installed on the floor level where the gas equipment is to be installed In addition the installing plumber or gasfitter shall observe that a batte...

Page 5: ...otated down for shipment In order to use the flanges remove the screw holding an individual flange rotate the flange so it is in the upward position and reinstall the screw then repeat this for all 4...

Page 6: ...CE ASSEMBLY PC SERIES COILS These upflow coils are designed for installation on top of upflow fur naces only If the coil is used with a furnace of a different size use a 45 transition to allow proper...

Page 7: ...will be necessary to seal the edges of the bottom panel to the casing using tape or other appropriate gasket material to prevent air leakage BOTTOM RETURN AND ATTIC INSTALLATIONS Bottom return applica...

Page 8: ...one support at the supply end of the furnace one support located approximately in the center of the furnace near the blower shelf and the third support should be at the return end of the fur nace Mai...

Page 9: ...Entry Gas Pipe Entry Thermostat Wiring FRONT 14 1 1 5 23 SUPPLY END C 24 38 20 5 B Gas Pipe Entry Thermostat Wiring 33 A 5 Electrical Entry Vent Connection Outlet Vent Connection Outlet 4 Diameter Ou...

Page 10: ...e of the furnace using any of the gas pipe entry on both sides of the furnace Refer to Figure 12 All filters and mounting provision must be field supplied All installa tions must have a filter install...

Page 11: ...1 0 87 0 73 0 67 1100 3 2 2 7 2 4 41 0 0 80 0 66 0 61 2500 LP 9 8 8 2 7 5 93 2 LP 2 44 2 03 1 86 TABLE 6 Nominal Manifold Pressure Low Fire First Stage Manifold Pressures in w c First Stage Manifold P...

Page 12: ...wn in Figures 17 or 18 Electronic thermostats may require the common wire to be connected Apply strain relief to thermostat wires passing through cabinet If air condition ing equipment is installed us...

Page 13: ...Volt Hot Cool XFMR W First Stage Heat Part Number S1 2HU16700124 1 G L 8 9 T F L 8 9 T PT 8 9 ID MODELS Part Numbers SAP Legacy 265903 031 09168 2 C 24 Volt Common R 24 Volt Hot W W1 First Stage Heat...

Page 14: ...n Y First Stage Compressor O B Reversing Valve L Malfunction Light Y2 Second Stage Compressor G Fan PP32U70124 THERMOSTAT E Emergency Heat R 24 Volt Hot Heat XFMR RC 24 Volt Hot Cool XFMR AUX Auxiliar...

Page 15: ...e 20 If furnace staging is desired with two single stage furnaces on a com mon duct where the gas burner on the first furnace operates on W1 and the gas burner on the second furnace operates on W2 the...

Page 16: ...to any type of B BW or L vent connec tor and shall be connected to a factory built or masonry chimney The furnace shall not be connected to a chimney flue serving a sepa rate appliance designed to bu...

Page 17: ...sub tracting the blockage area of all fixed louvers grilles or screens from the gross area of the opening 2 Apertures in a fixed louver a grille or screen shall have no dimen sion smaller than 0 25 0...

Page 18: ...nal area as the free area of the air supply inlet opening to which it connects 4 The blocking effects of louvers grilles and screens must be given consideration in calculating free area If the free ar...

Page 19: ...ng placed into operation while all other appliances connected to the venting system are not in operation 1 Inspect the venting system for proper size and horizontal pitch Determine that there is no bl...

Page 20: ...natural gas input rate by clocking meter 1 Turn off all other gas appliances and pilots 2 Run furnace for a minimum of 3 minutes in heating operation 3 Measure time in sec for gas meter to complete 1...

Page 21: ...22 164 327 818 64 56 112 281 23 157 313 783 66 54 109 273 24 150 300 750 68 53 106 265 25 144 288 720 70 51 103 257 26 138 277 692 72 50 100 250 27 133 267 667 74 48 97 243 28 129 257 643 76 47 95 23...

Page 22: ...essure by adjusting gas valve regulator screw for the appropriate gas per the following 4 After the manifold pressure has been adjusted re calculate the furnace input to make sure you have not exceede...

Page 23: ...urnace but not so long that cold air is blown into the heated space The fan off timing may be adjusted by positioning the jumper on two of the four pins as shown in Figure 26 MANIFOLD PRESSURE U TUBE...

Page 24: ...Low 1425 1380 1409 1378 1307 1274 1226 1180 1113 1025 120C20 High 2701 2620 2533 2429 2338 2227 2112 1993 1861 1706 Medium High 2125 2083 2046 1994 1955 1901 1857 1737 1621 1497 Medium Low 1664 1664...

Page 25: ...warm up period the gas valve then opens the gas starts to flow ignition occurs and the flame sensor begins its sensing function The blower motor will energize 30 seconds after the gas valve opens if a...

Page 26: ...description of 5 Red Flashes and 11Red Flashes below If the main limit switch opens five times within a single call for heat the control will indicate 4 Red Flashes and will enter a one hour soft loc...

Page 27: ...ill flash three green flashes when the memory has been cleared then will resume the normal slow green flash after a five second pause SECTION X REPLACEMENT PARTS LIST DESCRIPTION MOTOR MOTOR DIRECT DR...

Page 28: ...with wiring material having a temperature ra ng of at least 221 F 105C 2 Blower motor speed connections shown are typical but may vary by model and application LEGENDE DS Commutateur de porte MOT Mote...

Reviews: