Johnson Controls Frick IDC Installation Operation & Maintenance Download Page 21

IDC INDUCED DRAFT EVAPORATIVE CONDENSERS

MAINTENANCE

S140-500 IOM (FEB 08)

Page 21

4.6  Belt Replacement and Tensioning

Replacement

When the decision is made to replace the belt, follow these 
steps:

1.  Lock out and tag the starter.

2.  After the power has been turned off and the motor guard 

removed, loosen the motor mount adjustment nuts.

3.  Move the motor until there is enough slack in the belt so 

it can be removed without prying.

4.  Remove the old belts and inspect for unusual wear.  Ex-

cessive wear may indicate problems with alignment or 
sheave damage.

5.  Use replacement belts from the factory to ensure a proper 

belt equivalent.

6.  Inspect other drive components such as bearings and 

sheaves for alignment, wear, lubrication, etc.

7.  Clean the sheaves of debris before installing the new 

belt.

8.  Install the new belt, align the drive, and tension the belt 

according to the procedures outlined here.

Tensioning

Proper belt tension is very important to ensure maximum 
belt life. If too little tension is applied, the belt will slip. Too 
much tension can reduce belt and bearing life. It is not recom-
mended that belt dressing be used when belt slippage occurs 
as this will damage the belt and cause premature failure.

1. Decrease the center distance between the sheaves (by 

turning the tensioning nut counter clockwise) so the 
sheaves are somewhat loose.

2. Apply tension to the belt by turning the tensioning nut 

clockwise. 

3. Operate the drive a few minutes to seat the belt in the 

sheave grooves. Observe the operation of the drive during 
start-up. A slight bowing of the slack side of the drive indi-
cates proper tension. If the slack side remains taut during 
the peak load, the drive is to tight. Excessive bowing or 
slippage indicates insuffi cient tension. If the belt squeals 
as the motor comes on, it is not tight enough.  The drive 
should be stopped and the belt tightened.

NOTE: Do not overtighten the drive. 

4. If the above procedure still results in the belt squealing, 

but the belt is still taut on the slack side, a more precise 
method of testing the belt tension must be used. In this 
case, use a belt-tensioning gage available from V-belt 
drive manufacturers or from the Factory. 

All belt tension measuring devices should include operating 
instructions. These are spring-loaded devices that use a 
hook to place tension on a stationary belt. Tension readings 
are observed at a point where the belt defl ects a predeter-
mined distance. Tension is usually applied at the belt span’s 
mid-point as measured between the tangent of belt contact 
for both sheaves. Reference 

Figure 4-5.  Belt Tensioning 

Schematic.

4.7  New Belt Run-in 

During initial startup of new belts, a belt run-in procedure is 
recommended. During start-up, follow these instructions:

During start-up, look and listen for unusual noise or vibra-
tion.  

1.  After shutting down and locking out the starter, check the 

bearings and motor.  If they feel hot, the belt tension may 
be too tight.

2.  Run the drive under full load for 24 hours of continuous 

operation. Running the belts under full load allows them 
to seat themselves into the grooves.

3.  After running the drive, check the tension of the belts. Re-

tension to the recommended values. This run-in procedure 
will reduce the future need for re-tensioning and will help 
extend the life of the belts.

4.8 Coil 

Assembly

An evaporative-cooled condenser’s operational readiness is 
dependent on the condition of the coil. Coils that are dirty, 
blocked from air-fl ow, or physically damaged may affect 
overall heat transfer capability of the IDC to a signifi cant 
degree.

Periodically conduct a visual inspection of the coil section 
and refrigerant line connections. Remove any airborne debris 
that may have collected on the face of intake louvers or on 
the coils themselves. If separate air fi ltration exists prior to 
the intake louvers, ensure that adequate “free area” exists 
to meet intake-air CFM requirements.

Further need for cleaning or repair of an IDC coil should be 
left to the judgement of a certifi ed or factory-trained service 
person. Contact the local Frick representative if a coil or its 
connections appears to have been signifi cantly damaged.

4.9  Water Makeup Requirements

At its rated capacity (given in tons), an IDC unit will evaporate 
3 gallons/min per 100 tons.

When the water evaporates, any impurities remain. Recircu-
lating water fl ow then requires refreshing to prevent eventual 
scale build up. A bleed-off valve is located on the spray pump 
discharge line to bleed off an equal amount of water to that 
evaporated. (3 GPM per 100 tons)

For conditions where the original water hardness is very high 
or a large number of airborne contaminants may be washed 
into the recirculating spray water, a higher bleed-off rate or 
chemical treatment may be required. Consult a local water 
treatment company for recommendations.

4.10 Water Treatment

If the condition of the water is such that constant bleed-off 
will not control scale and/or control the recirculating water 
pH level within the acceptable range listed below, chemical 
treatment may be required. If a water treatment program 

Figure 4-5. Belt Tensioning Schematic

Summary of Contents for Frick IDC

Page 1: ...om for the latest version of this publication IDC INDUCED DRAFT EVAPORATIVE CONDENSERS Form S140 500 IOM FEB 2008 INSTALLATION OPERATION MAINTENANCE File SERVICE MANUAL Section 140 Replaces S140 500 I...

Page 2: ...rt up Operation 16 3 1 Initial Start up for new IDC Units 16 3 2 Initial and Seasonal Start Up 16 3 3 24 Hour Run In 17 3 4 Daily Operation 17 3 5 Seasonal Start up Shutdown 17 3 6 Winter Operations 1...

Page 3: ...gure 2 2 Eliminator Orientation Cross Section 12 Figure 2 3 Louver Installation 12 Figure 2 4a Assembly and Placement 13 Figure 2 4b Assembly and Placement 14 Figure 2 5a Vibration Isolator Feet 15 Fi...

Page 4: ...d utilizes the finest in engineered design materials and corrosion protection to provide a rugged long lasting unit This manual provides the information needed for safe installation operation and main...

Page 5: ...ports and installing the IDC condenser Adequate space must be continuously available to allow adequate airflow to the IDC inlet louvers to prevent discharge air recirculation Figure 1 2 IDC Unit to Un...

Page 6: ...IDC INDUCED DRAFT EVAPORATIVE CONDENSERS INSTALLATION S140 500 IOM FEB 08 Page 6 Figure 1 2 IDC Unit to Unit Spacing Requirements...

Page 7: ...IDC INDUCED DRAFT EVAPORATIVE CONDENSERS INSTALLATION S140 500 IOM FEB 08 Page 7 Figure 1 3 IDC Unit to Wall Spacing Requirements Multiple Cell and Multiple Unit Installation...

Page 8: ...et set Belt tension gage Tape measure 2 2 Foundation Information IDC units are shipped in two pieces a pan section and the fan coil section As the unit s base the pan section must first be anchored to...

Page 9: ...DENSERS INSTALLATION S140 500 IOM FEB 08 Page 9 Figure 2 1a 12 x 12 Foundation Layout OVERALL MODEL APPLICABLE CELLS LENGTH WIDTH 420 540 A 145 141 840 2S 1080 2S A D 145 286 840 2E 1080 2E A B 294 14...

Page 10: ...NSERS INSTALLATION S140 500 IOM FEB 08 Page 10 Figure 2 1b 12 x 18 Foundation Layout OVERALL MODEL APPLICABLE CELLS LENGTH WIDTH 575 835 A 211 141 1120 2S 1620 2S A D 211 286 1150 2E 1670 2E A B 426 1...

Page 11: ...NSERS INSTALLATION S140 500 IOM FEB 08 Page 11 Figure 2 1c 12 x 20 Foundation Layout OVERALL MODEL APPLICABLE CELLS LENGTH WIDTH 870 990 A 245 141 1690 2S 1920 2S A D 245 286 1740 2E 1980 2E A B 494 1...

Page 12: ...5 a b Vibration Isolator Installation and the following instructions ISOLATOR FEET INSTALLATION 1 Refer to the submitted foundation layout drawing for the correct location of each isolator and suppor...

Page 13: ...d Placement NOTES 1 The hook of the crane must be a minimum height above the top of the section being lifted to prevent excessive strain on the lifters 2 Safety slings and skidding should be removed b...

Page 14: ...IDC INDUCED DRAFT EVAPORATIVE CONDENSERS INSTALLATION S140 500 IOM FEB 08 Page 14 Figure 2 4b Assembly and Placement...

Page 15: ...aterally with the weight on the isolators If it is necessary to move the unit remove the weight from the isolators by raising the unit before moving Failure to follow this procedure could result in da...

Page 16: ...art up and operate any electrical cool ing equipment such as an IDC condenser unit it is essential that all personnel associated with have a basic knowledge of how and why the unit operates in normal...

Page 17: ...ol of the pan water level The system consists of a weather protected electric float switch with stilling chamber mounted on the pan section and a weather protected solenoid valve mounted on the water...

Page 18: ...NTHS MONTHS MONTHS Inspect General Condition of Unit X X Clean debris from unit X X X Clean and flush sump X X X Clean sump strainer X X X Check and adjust sump water level X X Inspect heat transfer s...

Page 19: ...L NUMBER PART NUMBER RECOMMENDED STOCK LEVEL FAN BELTS __________________________________________________ One Set FAN BEARINGS _______________________________________________ One Set FAN BUSHING _____...

Page 20: ...earings used on the belt drive IDC units are prelubricated with grease chosen for its chemical and mechanical stability in an evaporitive cooling environment The type of grease used is lithium complex...

Page 21: ...e belt span s mid point as measured between the tangent of belt contact for both sheaves Reference Figure 4 5 Belt Tensioning Schematic 4 7 New Belt Run in During initial startup of new belts a belt r...

Page 22: ...is an important part of the water treatment process During passivation operate the condenser as follows Clean all surfaces Maintain pH levels as close to 7 0 as possible Do not allow the pH to fall b...

Page 23: ...compound or Zinc solder If surrounding components will not be damaged by flame lev el heat a blowtorch can be used to slowly heat the scratch to the melt point of a Zinc solder rod Apply the Zinc unti...

Page 24: ...remote pump applications water must be supplied at the pressure and flow rate specified on the customer drawings Possible Cause 4 Inadequate Water Distribution In the event that a few nozzles prove to...

Page 25: ...eup valve assembly and refill basin to operat ing level Possible Cause 3 Pump Output Incorrect Take flows and pressure readings from pump piping in question Determine if pump may be throttled with mea...

Page 26: ...00 44 25 2 140 70 686 95 040 28 013 840 2S 595 8 162 594 2 15 1 430 2 5 2 6 PE 2 10 PE 1 200 198 00 30 25 850 32 198 45 022 11 957 870 2S 617 0 169 732 2 20 1 430 2 5 2 6 PE 2 10 PE 1 200 198 00 30 2...

Page 27: ...IDC INDUCED DRAFT EVAPORATIVE CONDENSERS INSTALLATION OPERATION MAINTENANCE S140 500 IOM FEB 08 Page 27 Figure 5 2 Standard IDC Series Unit Dimensions...

Page 28: ...ns precise control 24 hours a day seven days a week I Q NET distributed architecture mean faster easier economical installations I Q NET delivers increased operating efficiency and lowers energy costs...

Reviews: