6.0 Installation instructions
6.1 General
The user must ensure that his employees are fully trained and supervised in the proper
working procedures to ensure their safety. The plant must be maintained in a safe condi-
tion.
Ensure that the equipment is correctly installed in a suitable location by technically quali-
fied personnel.
Installation must meet the requirements of EN/IEC 60335-1, EN/IEC 60335-30.
6.2 Heater installation
Before unpacking the equipment ensure that all items are available and that all crates /
or packages are in good condition and undamaged. Any damages must be reported to
the site manager and subsequently to JEVI A/S.
After removing the packing material, check all items for damage. If any damages; report
this to the site manager and subsequently to JEVI A/S.
For installation mounting and sealing materials must be used which are suitable for the
medium to be heated and the prevailing temperatures that will occur. Please refer to the
GA-drawing for precise data and indications of fitting positions.
1. Open the junction box.
2. Connect the electric power cables to the terminals or bus bar system as indicated on
the electrical diagram and connect the earthing provisions on the mounting plate.
3. Connect the protective conductor to the earthing terminal.
Follow the instructions provided by the supplier of the cable glands if these are present
and/or applicable.
4. Close the cover.