- Clean all threaded parts with brake cleaner, dry it off with a clean paper towel
- Apply a good amount of PU sealant on both threaded parts before connecting them
- make sure the complete surface of thread is covered in PU sealant
- Remove any left over PU Sealant with the special wet wipes in the round can
-
Attention, the wet wipes are for removing afterwards the left over sealant. Do not clean upfront the
threaded parts with the wet wipes. This will cause the sealant not to bond and will cause leakage!!!
5: Water inlet and acces to shut off valve
- Ball valve must be easily accessible
- Inlet hose max 1 meter long, shorter always possible
- Installation of water inlet may be possible from the side of the vessel
- Water inlet below waterline. Position higher than pump is allowed
- Remove antifouling under flange
- Use supplied Stainless steel tool to twist water inlet into 90-degrees turn
6: Hose clamps and connection:
- Use grease on the bolts
- Prevention against corrosion (Vaseline spray)
7: Hose routing
Summary of Contents for D-010-07
Page 2: ......