SECTION 10
CAMPING & OPERATING
6.
Level the park trailer within reasonable
tolerances, using a 6 foot carpenter’s
level, water level or similar equipment.
The final height adjustment is obtained by
jacking the “I”-beam and placing
hardwood shims between the piers and
“I”-beam, or other approved methods such
as adjustable piers.
This leveling
process is important for appearance
and is essential for the proper
operation of doors, windows and the
drainage system.
7. Within 90 days after initial setup, the park
trailer should be re-leveled, if necessary,
to compensate for any pier settlement.
Follow the procedure in Item 6 above.
During the leveling or re-leveling
process, loosen the frame ties and
over-the-roof ties (if provided) prior to
jacking the unit.
Tie-down instructions
All park trailers should be securely anchored
to the ground with 6 tie-downs and ground
anchors (minimum 3 per side), to resist the
sliding and overturning effects of high winds.
Where tie-downs are required, it will be
necessary to follow the instructions herein.
Frame tie-down procedure
All park trailers are equipped with tie-down
attachment provisions on the main “I”-beams
(See Fig. 10.7). Any one of the three methods
featured may be used.
In the tie-down system, it is important to
use materials of proper design and of
adequate quality. The material
specifications contained herein should be
considered as minimum requirements.
Materials not furnished with the park trailer
which will be necessary to complete the tie-
down system must meet the requirements set
forth below. Such materials would include:
1. Cable or steel strap with a breaking
strength of at least 4,725 pounds, e.g.
galvanized aircraft cable at least 1/4” inch
in diameter or Type 1, Finish B Grade 1
steel strapping, 1 1/4 inches wide and
0.035 inches thick, conforming with F.S.
QQ-S-781-H.
2. Galvanized connection devices such as
turnbuckles, eyebolts, strap buckles and
cable clamps should be rated at 3,150
working load minimum.
3. Ground anchors capable of withstanding
at least a 4,725 pound pull. Anchors must
be installed as specified by the anchor
manufacturer.
THE UNIT MUST BE IN ITS FINAL LEVEL
POSITION PRIOR TO TYING IT DOWN.
The procedure for tying down the park trailer
is as follows:
1. Position and install the ground anchors to
line up with the provided tie-down
brackets.
2. Connect the straps to the frame and
ground anchors.
3. Tighten the straps using the tensioning
device provided with the ground anchors.
Use caution to avoid over-tensioning the
straps as this may pull the trailer off the
piers. It is recommended that all straps be
tightened only enough to remove the
slack. Then, after all THE straps are
installed and the slack removed, tension
the straps.
4. The strap tension should be rechecked at
frequent intervals until all pier settlement
has stopped.
Fig. 10.6 Frame tie-down diagram
During the re-leveling process, do not jack
the park trailer against tight straps.
71
Summary of Contents for JAY FLIGHT BUNGALOW 2010
Page 1: ...www jayco com Owner s Manual Model Year 2010 P N 0190626 2010 PA R K T R A I L E R S...
Page 26: ...SECTION 2 OCCUPANT SAFETY 22 THIS PAGE IS INTENTIONALLY BLANK...
Page 34: ...SECTION 3 PRE TRAVEL INFORMATION 30 THIS PAGE IS INTENTIONALLY BLANK...
Page 60: ...SECTION 7 PLUMBING SYSTEMS 56 THIS PAGE IS INTENTIONALLY BLANK...
Page 68: ...SECTION 8 PROPANE SYSTEM 64 THIS PAGE IS INTENTIONALLY BLANK...
Page 84: ...SECTION 10 CAMPING OPERATING 80 THIS PAGE IS INTENTIONALLY BLANK...