INSTALLATION OF THE FIREBRICKS
1.
Before you begin, please take note that the purpose for the screws is to secure the
bricks inside the stove.
2.
First, install the bricks C (10), F (2), E (1) at the bottom of the stove and C (1) &
D (1) on the inclined part near the door.
3.
Second, install the bricks to the bottom of the back wall 4 (C),1 (A) pre-screw the
brick supports and screws add C(2) and E(1),when all bricks and supports are
installed you can then tighten the screws.
4.
Third, install C (12) B (2) A (2) E (2) bricks on the side wall.
5.
To install the last top bricks, the rock wool and the retaining plate, follow the last
step before lighting the stove.
-
Add the 3 bricks on the pipes. Then add the rock wool and the 2 retaining plates on
the bricks. To finish the installation, put the last 3 bricks between the first and the
second pipe and put-it on the pipes.
BRICKS:
Qties
A 2 ¼” X 9” :
3
B 5” X 9” with 1” angle:
2
C 4 ½” X 9” :
35
D 6 ½ X 4 ½” :
1
E 4 ½” 4 ½“ :
4
F 4 ½” X 2 ¼” :
2
G brick support:
3
H screws for support:
3
***Please take note that that step 1 to step 3 is already done at the factory***