Installation Instructions
Hanger Installation:
9'
(108.0")
4'
(48.0")
Burner
Side
Baffle
Side
First
Hanging
Point
Second
Hanging
Point
Third
Hanging
Point
9'
(108.0")
4'
(48.0")
Burner
Side
Baffle
Side
First
Hanger
Second
Hanger
Third
Hanger
Locate hanging points at predetermined suspension points in the
structure. A minimum 12" length welded link chain with a working load
of at least 200 lbs is recommended.
it is required that the first 2 hangers be about 9' (108")
away and the third hanging point is 4' (48"), as shown.
Install the hangers to chains using a chain link or "S-Hooks". When
"S-Hooks" are used close all open ended "S-Hooks" turnbuckles to
avoid unhooking chain with inadvertent contact.
12" Min.