1. Setup the Equipment Number
1) Setup the equipment number in accordance with wiring conditions by using rear panel DIP switch.
2) Setup method is shown in below table, and number on the ON switch will be the equipment number.
?
Caution: Zone display LED will brink if equipment number is not set.
Communication will not be available if equipment numbers are duplicated.
Check the equipment number setting in above case.
3) Zone allocations of set equipment are as follow.
2. TERMINATION Switch (LOAD/OPEN) Setting
1) Termination switch on the rear panel should be set (Load/Open) to stabilize the data transfer in case of
the system linked by using RS-485 communication.
2) Setup the termination switch to LOAD in the equipment which link is started first time and equipment which
link is ended. Setup the other equipment to Open.
?
Caution: Communication error may occur if setup is wrong.
DIP Switch 1 2 3 4 5 6 7 8 9 10
1 ON
2 ON
Equipment
3 ON
No.
10 ON
Equipment No. 1 2 3 4 5 6 7 8 9 10
ZONE Allocation 1~16 17~32 33~48 49~64 65~80 81~96 97~112 113~128 129~144 145~160
Equipment 1
S/W: LOAD
IN
OUT
Equipment 2
S/W: OPEN
IN
OUT
Equipment 3
S/W: OPEN
IN
OUT
Equipment N
S/W: LOAD
IN
OUT