Instruction Manual
|
8
T: 303-833-6644
or
800-666-1611
www.inteccorp.com
Original Language - English
Set up and Operation
System Set-Up:
Set system on a dry, level surface.
1.
Obtain appropriate protective equipment.
a.
Recommendations: dust mask, eye protection, gloves, knife
to cut insulation bags, and a hat.
2.
Power Connections:
FORCE/3 HP2:
Obtain three 12 gauge, heavy duty twist-lock power cords (note: when requiring
over 100 feet per power cord, recommendation is to use 10 gauge in order to reduce the
voltage drop and allow for appropriate operation of motors). Connect one power cord to each
blower power receptacle, and one to the agitator & airlock power inlet. Note that each power
source is required to be an
independent
115V - 15 amp (or greater) circuit.