Right the frame from a prone position
Product Support:
•
The load frame is bolted to the shipping skid.
•
There are no loose accessories on the shipping skid.
•
Ensure that there is adequate ceiling clearance to allow the load frame to be lifted
into a vertical position, including clearance for the crane (refer to
).
•
Operators of any lifting equipment have the appropriate licenses and have complied
with your local safety standards (e.g. the appropriate training required by OSHA in
the U.S.).
Procedure
1. Remove all packaging material from the frame but DO NOT remove any of the bolts
and brackets that attach the frame to the shipping skid.
2. Attach the two lifting slings to the crosshead and secure them to the crane hook as
shown in
. If you use chains in lieu of lifting slings, wrap protec-
tive material around the crosshead to protect the crosshead from scratching and
marring. Chains can also cause damage to other parts of the frame, the top plate for
example; be sure to wrap protective material around all vulnerable components.
3. Install two M16 hoist bolts into the frame base and attach two additional slings to the
bolts, as shown in
.
Summary of Contents for 34FM-100
Page 1: ...Model 34FM 100 Dual Column Floor Model Preinstallation Manual M10 17541 EN Revision A...
Page 8: ...Preliminary Pages 8 M10 17541 EN...
Page 12: ...Preliminary Pages 12 M10 17541 EN...
Page 50: ...Chapter Specifications 50 M10 17541 EN...
Page 58: ...Chapter Risk reduction and safe use 58 M10 17541 EN...
Page 72: ...Chapter Lifting and handling 72 M10 17541 EN...
Page 74: ...74 M10 17541 EN...
Page 75: ......
Page 76: ...www instron com...