6. Installing the unit
Before installing the unit, you must remove the packaging, taking special care not to damage the housing.
Check that there is no condensation inside the packaging. If there are signs of condensation, the unit must not be
installed until you are sure it is completely dry.
All installation operations must comply with current regulations.
All operations involving moving heavy weights must be carried out by two people.
6.1. General requirements for installation
•
The environment of the unit must be appropriate and meet the guidelines described in Chapter
Preparation for installing the unit”
. Additionally, the parts used in the rest of the installation must be
compatible with the unit and comply with the applicable legislation.
•
Ventilation and the space for work must be suitable for maintenance tasks according to the applicable
regulations in force.
•
The external connection devices must be suitable and sufficiently close as set forth in current regulations.
•
The feed cables must be of the appropriate gage for the maximum current.
•
You must take special care to ensure that there are no external elements near the air inlets and outlets
that obstruct proper cooling of the unit.
6.2. Attaching the unit to the wall
These units have a system for securing them to the wall using a plate. The steps for fixing the unit properly are as
follows. The weight of the unit must be taken into account.
The top attachment plate for the unit supports the weight. The bottom point fixes the inverter to the wall and
prevents vibrations.
1. Mark the fixing points for the plates on the wall.
200 mm (7.87 in)
324 mm (12.76 in)
2. Drill holes in the wall with a suitable bit for the fastening elements to be used to secure the plate to the
wall later.