Start Up
28
RT-SVX51B-EN
. The appropriate oil
charge is listed in
2. After the compressor and condenser fan have started
and operated for approximately 30 minutes, observe
the operating pressures. Compare the operating
pressures to the operating pressure curve in the
Service Facts.
3. Check system subcooling. Follow the instruction listed
on the subcooling charging curve in the Service Facts.
4. Repeat
circuit.
5. To stop the SERVICE TEST, turn the main power
disconnect switch to the “Off” position or proceed to
the next component start-up procedure. Remove
electro mechanical test mode connections (if
applicable).
Heating Start-Up
Using the Service Test Guide perform the proper test mode
connections.
When starting the unit for the first time or servicing the
heaters, it is a good practice to start the heater with the
main gas supply turned “Off”. Once the ignition system and
components have been checked, open the main power
disconnect switch to reset the unit.
Final System Set Up
After completing all of the pre-start and start-up
procedures outlined in the previous sections (i.e.,
operating the unit in each of its modes through all
available stages of cooling and heating), perform these
final checks before leaving the unit:
•
Program the Night Setback (NSB) panel (if applicable)
for proper unoccupied operation. Refer to the
programming instructions for the specific panel.
•
Verify that the Remote panel “System” selection
switch, “Fan” selection switch, and “Zone
Temperature” settings for automatic operation are
correct.
•
Inspect the unit for misplaced tools, hardware, and
debris.
•
Verify that all exterior panels including the control
panel doors and condenser grilles are secured in place.
•
Close the main disconnect switch or circuit protector
switch that provides the supply power to the unit’s
terminal block or the unit mounted disconnect switch.
Table 7.
Compressor types
Tonnage
C1
C2
GA*180
SSA083
SSA076
GA*210
SSA091
SSA083
GA*240
CSHD142
SSA083
GA*300
CSHD155
SSA083
Table 8.
POE Oil recharge amount (fl. oz.)
Model
C1
25mm
C2
25mm
GA*180
56
56
GA*210
56
56
GA*240
112
56
GA*300
112
56