1.17 SEPARATOR KIT INSTALLATION
Type C configuration, sealed chamber and fan assisted,
separator kit Ø 80/80
This kit allows air to come in from outside the building and the
exhaust to exit from the chimney, flue or intubated duct through
divided flue exhaust and air intake pipes.
Combustion products are expelled from pipe (S) (in plastic, so as
to resist acid condensate).
Air is taken in through duct (A) for combustion (this is also in pla-
stic).
The intake pipe (A) can be installed either on the right or left hand
side of the central exhaust pipe (S).
Both ducts can be routed in any direction.
Mounting the separator kit Ø 80/80 (Fig. 26):
1. Install the flange (4) on the central hole of the boiler, positio-
ning gasket (1) with the circular projections downwards in
contact with the boiler flange.
2. Tighten with the hexagonal head and flat point screws provi-
ded in the kit.
3. Replace the flat flange present in the lateral hole with respect to
the central one (according to needs) with the flange (3), posi-
tioning the gasket (2) already present in the boiler
4. Tighten with the supplied self-tapping screws with drill bit.
5. Fit the bends with male side (smooth) (5) in the female side of
the flanges (3 and 4).
6. Fit the intake terminal (6) with the male side (smooth) in the
female side of the bend (5) up to the end stop, ensuring that the
internal and external wall sealing plates are fitted
7. Fit the exhaust pipe (9) with the male end (smooth) to the fe-
male end of the bend (5) up to the end stop; making sure that
the internal wall sealing plate has been fitted, this will ensure
sealing and joining of the elements making up the kit.
C52* - C82
1
4
7
9
5
5
6
7
8
3
2
S
A
26
The kit includes (Fig. 26):
No.1 Exhaust gasket (1)
No.1 Flange gasket (2)
No.1 Female intake flange (3)
No.1 Female exhaust flange (4)
No.2 Bend 90° Ø 80 (5)
No.1 Intake terminal Ø 80 (6)
No.2 Internal wall sealing plates (7)
No.1 External wall sealing plate (8)
No.1 Exhaust pipe Ø 80 (9)
*
to complete C52 configuration, also provide for a “green range” roof
discharge terminal.
The configuration on walls opposite the building is not allowed.
Installation clearances (Fig. 27)
The minimum installation clearance measurements of the Ø
80/80 separator terminal kit have been stated in some limit condi-
tions.
C42
27