3.7 REVERSING THE CONNECTIONS
The ARES Tec ErP boiler leaves the factory set up for hydraulic (flow
and return), gas and flue exhaust connections located on the RIGHT
side of the boiler.
Reversing FLUE GAS
To move the flue exhaust to LEFT simply switch the two sides of the
casing around.
FOR MODELS 250 - 300 - 350
To move the flue exhaust from Right (standard posi-
tion) to the rear position, you need to request the
optional flue kit consisting of the Ti shown in the
figure and a closing plate for the hole in the Rh side
of the casing.
FOR MODELS 150 - 200
it is necessary to request the flue kit comprised of a
closing plate over the hole on the Rt side of the casing. .
Reversing GAS
To move the gas connection,
switch the blind flange with
the flanged stub pipe.
Reversing SYSTEM FLOW AND RETURN
To move the Flow / Return connections to the opposite side,
switch the blind flange with
the flanged stub pipe.
To move the hydraulic
connections (one or both) to
the LEFT side, remove the
pre-sectioned part on the
attachments that you intend to
move to the opposite side and
close the RIGHT side of the
casing with the caps supplied
with the boiler.