29
Mexico Super CF 3/100, 3/125, 3/140 -
Installation
48 GAS VALVE REPLACEMENT
SERVICING
49 TTB DOWNDRAUGHT THERMOSTAT REPLACEMENT
1.
Remove the control panel. Refer to Frame 41.
2.
Remove the securing screws and lift off the control
box cover.
3.
Disconnect the TTB thermostat and remove from
the cable clamp and control box. Refer to Frame
54.
Note.
The TTB thermostat is located at the LH or
RH side of the diverter panel.
4.
Reach down the side of the boiler and carefully lift
the TTB bracket from its retaining slot and clip.
5.
Withdraw the thermostat, bracket and lead down
the side of the boiler.
6.
Locate and fit the new TTB downdraught
thermostat, bracket and lead and re-assemble in
reverse order, ensuring that all electrical
connections are correctly remade and cables
secured.
Note
.
CF 3/100
If minimum LH side clearance is used on the CF 3/100
boilers, the
TTB downdraught thermostat
and bracket
should be moved to the RHS of the boiler (alternative
location).
1.
Lift off the front panel and remove
the grille assembly. Refer to
Frames 28 & 29.
Remove the burner and controls
assembly.
2.
Undo the pilot supply connection.
3.
Undo the thermocouple
connection.
4.
Unscrew the gas inlet pipe from
the valve.
5.
Remove the 4 securing screws
and withdraw the valve from the
burner manifold.
6.
Fit the new gas valve, ensuring
that:
a.
The valve is fitted the correct
way round - an arrow engraved
on the valve indicates the
direction of flow.
b.
The sealing 'O' ring supplied
with the valve is correctly fitted
at the outlet flange.
c.
An approved jointing compound
is used when reconnecting the
gas inlet pipe.
SER
VICING
Summary of Contents for CF#/125