background image

ELEVATION SERIES

REMOTE CONDENSER GUIDELINES

4

Remote Condenser Installation

For proper operation of the ice machine, the following installation guidelines must be followed. Failure to 

do so may result in loss of production capacity, premature part failure, and may 

void all warranties

.

Use the following for planning the placement of the remote condenser relative to the ice machine

Location Limits

Remote condenser location must not exceed 

ANY

 

of the following: 

Maximum rise from the ice machine to the 

remote condenser is 35 physical feet.

Maximum drop from the ice machine to 

the remote condenser is 10 physical feet.

Physical line set maximum length is 75 ft.
Calculated line set length maximum is 100 

ft.

Ambient operating temperatures:                                

ƒ)ƒ&WRƒ)ƒ&

Calculation Formula

Drop = dd x 6.6 

(dd = drop distance (ft.))

Rise = rd x 1.7 

(rd = rise distance (ft.))

Horizontal Run = hd 

(hd = horizontal distance (ft.))

Calculated Line Length = Drop + Rise + Horizontal Run

Configurations that do NOT meet these 

requirements must receive written authorization 

from Ice-O-Matic. This includes multi-pass or rack 

system remote condensers

DO NOT: Route a line set that rises, then falls, then
rises or a line set that falls, then rises, then falls

Remote Condenser Location

Pre-charged line sets are available in 25, 40, 45, 60 
or 75 foot length to connect the ice machine to the 
remote condenser. Select the best available 
location, protecting the remote condenser from 
extremes of dirt, dust and sun. Meet all applicable 
building codes. The services of a licensed 
electrician may be required.

Roof Attachment 

Install and attach the remote condenser to the roof 
of the building using the methods and practices of 
construction that conform to the local building 
codes, including having a roofing contractor secure 
the remote condenser to the roof. 

Have an electrician connect the remote condenser 
fan motor wires to the ice machine using the 
junction box at the back of the machine.

Pre-charged Line Set Routing

CAUTION: Do not connect the pre-charged tubing 

until all routing and forming of the tubing has been 

completed. See the coupling instructions for          

connecting information

Each set of pre-charged tubing refrigerant lines 
consists of a 3/8 diameter liquid line and 1/2 inch 
diameter discharge line. Both ends of each line 
have quick connect couplings, one end of the line 
set has a Schrader valve connection.

Note: 

the openings in the building or ceiling or wall, 

listed in the next step, are the minimum sizes 

recommended for passing the refrigerant lines through.

Have a roofing contractor cut a minimum hole for 
the refrigerant lines of 2.50 inch. Check local 
codes, a separate hole may be required for the 
electrical power to the condenser. 

CAUTION: DO NOT KINK OR CRIMP 

REFRIGERANT TUBING WHEN INSTALLING 

IT

Summary of Contents for CIM0320HA

Page 1: ...Ice O Matic 11100 East 45th Avenue Denver Colorado 80239 1 800 423 3367 9081484 01 REV E 11 2017 s d KE Z h D Z D K D...

Page 2: ...r inspection by the carrier within 5 days of the delivery date then file a claim on a form from the carrier FILE CLAIMS WITHOUT DELAY DO NOT RETURN DAMAGED GOODS TO ICE O MATIC How to use this Manual...

Page 3: ...es Use 3 8 inch O D minimum on air cooled machines On water cooled machines 3 8 inch O D minimum tubing must be run to the condenser The water supply for the machine can T off from the condenser line...

Page 4: ...been supplied Make sure the machine is on a dedicated circuit European installations require that the electrical supply fixed wiring must be provided with a disconnect means having a separation of at...

Page 5: ...oot length to connect the ice machine to the remote condenser Select the best available location protecting the remote condenser from extremes of dirt dust and sun Meet all applicable building codes T...

Page 6: ...enser manual The following remote ice makers incorporate the Mixing Valve in the condenser This configuration allows up to a 100 foot calculated remote line set run Reference the diagram on the next p...

Page 7: ...Formula for maximum equivalent run RISE x 1 7 DROP x 6 6 HORIZONTAL RUN EQUIVALENT RUN NOT TO EXCEED 100 CALCULATED FEET Rise 35 ft x 1 7 40 ft 99 5 equivalent feet line run Drop 10 ft x 6 6 34 ft 10...

Page 8: ...Hole for electrical connections 7 8 D Electrical junction box 7 8 CIM 2 W R Water Remote Cooled A Ice maker potable water in 3 8 FPT B Ice maker water out 3 4 FPT C Hole for electrical connections 7 8...

Page 9: ...Hole for electrical connections 7 8 D Electrical junction box 7 8 CIM 3 W R Water Remote Cooled A Ice maker potable water in 3 8 FPT B Ice maker water out 3 4 FPT C Hole for electrical connections 7 8...

Page 10: ...usion of Anti Slush the unit will continue in freeze mode until the Low Water Float is satisfied closes indicating the formation of a full slab of Ice on the Evaporator and will start the harvest Cycl...

Page 11: ...plained in this section Bridge Thickness Adjustment Once the unit has gone through a harvest cycle verify the bridge thickness 3 16 thick for units less than 400 lbs and 1 8 for 400 lbs and above acro...

Page 12: ...er thickness and adjustment procedure 3 Check water level in Sump See page 10 for proper water level and adjustment procedure 4 Clean the condenser air cooled machines to ensure unobstructed air flow...

Page 13: ...r such as Nu Calgon IMS III or equivalent diluted per manufacturer s instructions Please refer to www iceomatic com for approved chemical formulations and proper pH balance CAUTION Do not mix cleaner...

Page 14: ...th a clean soft cloth the evaporator water spillway water distributor upper evaporator cover lower evaporator curtain and all splash surfaces Verify that all residue and residual minerals have been re...

Page 15: ...g your machine looking like new 1 Clean the stainless steel and aluminum thoroughly once a week Clean frequently to avoid build up of hard stubborn stains Hard water stains left to sit can weaken the...

Page 16: ...evaporator s If ice is being made initiate harvest by pressing the Power Button for approximately 3 seconds The unit will shut off automatically following the harvest 3 Disconnect the tubing between t...

Reviews: