INSTALLATION AND OPERATION INSTRUCTIONS
1-18
SL 14-115 G3, SL 20-160 G3, SL 30-199 G3 MODULATING GAS BOILERS
SL 14-115 G3, SL 20-160 G3, SL 30-199 G3 MODULATING GAS BOILERS
1.5.3 Condensate Trap Assembly - cleaning procedure
1. Turn off the power to the boiler and allow it to cool down.
2. Remove the trap from the boiler (reverse the installation procedure above).
3.
Remove the Trap Cleanout Assembly (H), from the Trap Body and clean and flush the
debris out.
4.
Re-assemble trap components, re-fill trap, and replace on boiler as described in the
installation instructions above.
1.5.4 Further installation details
• Condensate drain must be piped to within 1” of a drain or be connected to a
condensate pump.
• Drainage line must slope down to the drain at a pitch of 1/4” per foot so condensate
runs towards the drain.
•
Condensate traps should be checked every 2 months, and cleaned and refilled as
necessary.
NOTE
It is the responsibility of
the installing and/or service
Contractor to advise and instruct
the end User in how to perform
the Trap cleaning procedure,
and to advise that the Trap
be checked at least every two
months and cleaned as required.
Summary of Contents for SL 14-115 G3
Page 71: ...6 3 DIAGRAMS SL 14 115 G3 SL 20 160 G3 SL 30 199 G3 MODULATING GAS BOILERS...
Page 73: ...6 5 DIAGRAMS SL 14 115 G3 SL 20 160 G3 SL 30 199 G3 MODULATING GAS BOILERS...
Page 75: ...6 7 DIAGRAMS SL 14 115 G3 SL 20 160 G3 SL 30 199 G3 MODULATING GAS BOILERS...
Page 81: ...SERVICE RECORD DATE LICENSED CONTRACTOR DESCRIPTION OF WORK DONE...
Page 82: ...NOTES...
Page 83: ...NOTES...