background image

4000 SRM 764

Three-Stage Mast

4.

Use a pry bar to move the inner mast weldment
approximately 1/2 to 3/4 out of the intermedi-
ate mast weldment. Remove the snap rings and
washers from the top of each main-lift cylinder.
Move the intermediate mast weldment approx-
imately 152 to 305 mm (6 to 12 in.) out from
the top of the outer mast weldment. Remove the
chain and remove the hose sheaves at the top of
the intermediate mast weldment.

5.

Install a sling near the center of each channel of
the inner mast weldment so it will be balanced.
The slings must pass through the loop at the end
of the sling so the sling tightens and does not slip
on the channel as the weldment is lifted. Fasten
a crane to the slings.

6.

Use the crane to move the inner mast weldment
out of the outer mast weldment. Move the mast
weldment until the bottom rollers of the inner
mast weldment touch the top rollers of the outer
mast weldment. Use the crane to raise the top
of the inner mast weldment so it is at an angle
of approximately 30°. Lift the weldment straight
up to remove the inner from the outer mast weld-
ment. Put the weldment flat on the floor so it
cannot fall.

7.

Use the procedure of Step 5 and Step 6 to remove
the intermediate mast weldment from the outer
mast weldment.

8.

Clean the area at the hydraulic fittings for the
main-lift cylinders. Disconnect the fittings. Put
caps on the open fittings and cylinder port to pre-
vent dirt from entering the system. Remove the
snap rings at the bottom of each cylinder.

9.

Install a sling near the center of one main-lift
cylinder in the same manner used for the mast
weldment removal.

Remove the capscrew,

washer, and spacer that fasten the cylinder to
the outer mast channel. See Figure 3. Use the
crane to move the cylinder out of the base hole
and remove the cylinder from the mast. Repeat
the procedure to remove the other main-lift
cylinder.

10. Remove the snap rings from all load rollers.

Make a note of the shim arrangement as each
load roller is removed. Remove the snap rings
from all the sheaves. Make a note of the shim
arrangement as each sheave is removed.

All

shim arrangements will be approximately the
same when the mast is assembled.

11. Remove the strip bearings from the outer mast

weldment. Make a note of the shim arrangement
during removal of the strip bearings for correct
installation during assembly.

12. Disassemble the sheaves and rollers as necessary

for repair and cleaning.

CLEAN AND INSPECT

The procedures for cleaning and inspecting the three-
stage masts are the same as the procedures for the
two-stage masts. See Clean and Inspect for the Two-
Stage Mast for the correct procedures.

LIFT CYLINDERS

NOTE:

The lift cylinders are removed during disas-

sembly of the mast. To repair the cylinders, see the
section Lift Cylinders 4000 SRM 135 for the correct
service procedures.

ASSEMBLE

NOTE:

The shims for the load rollers keep the chan-

nels of the mast weldments parallel and give correct
clearance. During assembly, the arrangement of the
shims will be the same or approximately the same as
they were before disassembly. Check the clearance
and adjust for wear or changes from the repairs. The
strip bearings at the top of the outer mast weldment
and the bottom of the inner mast weldment are also
adjusted using shims. See the Checks and Adjust-
ments in this section for the instructions to make the
necessary adjustments. See Figure 4 and Figure 12.

1.

Assemble the load rollers, sheaves, and strip
bearings on the mast weldments and operator
platform as necessary.

Assemble the sheaves

on the free-lift cylinder. Make sure to keep the
same shim arrangement noted during disassem-
bly. Apply a thin layer of multipurpose grease
to the strip bearings and the bearing and roller
surfaces of the channels.

2.

Make sure the cylinders are assembled and in-
stall a sling near the center of one main-lift cylin-
der as during removal. Use a crane to move the
cylinder into position in the outer mast weld-
ment.

Install the snap ring on the bottom of

the cylinder. Install the capscrew, washer, and
spacer to fasten the cylinder shell to the chan-
nel. Repeat the procedure to install the other
main-lift cylinder.

15

Summary of Contents for A169

Page 1: ...MAST REPAIR R30XMF3 A169 R30XMA3 A185 N40 50EA N40 45ER C138 R30E EA R30EA FS D118 R30XMS2 D174 R30XMS3 E174 R30XM XMA XMF F118 R30XM2 R30XMA2 R30XMF2 G118 R30XM3 H118 PART NO 1466835 4000 SRM 764...

Page 2: ...cifications of the original equipment manufacturer Make sure all nuts bolts snap rings and other fastening devices are removed before using force to remove parts Always fasten a DO NOT OPERATE tag to...

Page 3: ...assemble 13 Clean and Inspect 15 Lift Cylinders 15 Assemble 15 Install 16 Load Wheels Replacement 17 Lift System Leak Check 17 Lift Chain Adjustment 18 Mast Adjustments 19 Operator Platform Adjustment...

Page 4: ...THE QUALITY KEEPERS HYSTER APPROVED PARTS...

Page 5: ...d to the operator plat form by a pin near the edge of the platform See Figure 1 and Figure 2 The pin fits through a tube welded to the top of the fork The forks can be re moved by raising the operator...

Page 6: ...Forks 4000 SRM 764 1 FORK 2 PIN 3 WASHER 4 WASHER 5 WASHER 6 SPACER 7 SHIM 8 PEDAL 9 PALLET GRIP 10 PAWL Figure 2 Forks Pallet Grip and Operator Platform 2...

Page 7: ...will disconnect the lift chain s without changing the chain adjustment Care fully move the lift chain s through the sheave s and lay the chain s over the top of the lift truck 6 Use a ladder for acces...

Page 8: ...NING RING 3 WASHER BACK 4 RUBBER BUSHING 5 SHIMS 6 SCREW 7 LOCKWASHER 8 CYLINDER RETAINER 9 CUSHION 10 MAIN LIFT CYLINDER 11 LOCK PLATE 12 SCREW 13 LOCKWASHER 14 LIFT CHAIN 15 CHAIN ANCHOR 16 OUTER MA...

Page 9: ...t truck frame WARNING Before installing lift chains or cables use blocks and chains on the mast weldments and operator platform so they cannot move Make sure the moving parts are attached to a non mov...

Page 10: ...en all the mast weldments to gether so they cannot move Operate the crane until it gives support to the weight of the mast Move the crane to a position so the mast assem bly will be lifted vertically...

Page 11: ...4000 SRM 764 Two Stage Mast Figure 4 Two Stage Mast Assembly 7...

Page 12: ...ing near the center of the lift cylin der in the same manner used for the mast weld ment removal Remove the capscrew washer and spacer that fastens the cylinder to the outer mast channel See Figure 3...

Page 13: ...IONS FOR MEASURING CHAIN WEAR ARE SHOWN ON THE CHAIN WEAR SCALE Pitch Total Lengths of 20 Links Pitch of New Chain Wear Limit The Maximum Length of 20 Links 12 7 mm 0 50 in 15 9 mm 0 625 in 19 1 mm 0...

Page 14: ...to move the cylinder into position in the outer mast weldment Install the snap ring on the bottom of the cylinder In stall the capscrew washer and spacer to fasten the cylinder shell to the channel Re...

Page 15: ...ast directly over the open trunnions and lower the mast until it rests on the trunnion blocks as shown in Figure 6 Make sure the align ment block is resting in the angled bracket shown in Figure 7 Ins...

Page 16: ...e hoist still attached to the platform raise the platform to a height that will allow for easy access under the platform NOTE If your truck is equipped with wire guidance refer to the Installation sec...

Page 17: ...hree stage mast is similar to the removal procedure for the two stage mast See Two Stage Mast Remove in this section for the correct procedure DISASSEMBLE NOTE This procedure does NOT include the remo...

Page 18: ...LIFT CYLINDER A LOCK PLATE B RETAINER 5 CHAIN ANCHOR 6 CHAIN SHEAVE ASSEMBLY RH A CHAIN SHEAVE B BALL BEARING C SNAP RING 7 MAIN LIFT CHAIN 8 LOAD ROLLER 9 FLOW REGULATOR HOUSING 10 HYDRAULIC TUBE MA...

Page 19: ...r is removed Remove the snap rings from all the sheaves Make a note of the shim arrangement as each sheave is removed All shim arrangements will be approximately the same when the mast is assembled 11...

Page 20: ...e chain anchors at the bot tom of the inner mast weldment Use new cotter pins during installation of the chains c Use the wires to pull the chains up between the chain sheaves and the top load rollers...

Page 21: ...system a Operate the hydraulic system Put a capacity load on the forks Make sure there is enough overhead clearance Raise and lower the load several times Check for leaks 2 Leaks inside the hydraulic...

Page 22: ...stments for wear 3 Remove the load from the forks Check the clear ance of the operator platform when the mast is fully extended The operator platform stops must not touch the stop at the top of the in...

Page 23: ...the following procedure to adjust the load rollers for the mast a Use a crowbar to move the mast weldments from side to side to measure the amount of movement Repeat in a minimum of three different p...

Page 24: ...th a thin layer of grease CAUTION Too much grease can cause the rollers to slide and wear flat areas on the rollers 6 Slowly raise and lower the mast several times without a load The mast components m...

Page 25: ...URE OR ACTION Rough movement of the mast assembly Air in the hydraulic system Purge air from system Bent rods cylinders with distortion or damage Repair or replace cylinders Mast assembly damaged or n...

Page 26: ...________________________________________ ____________________________________________________________ ____________________________________________________________ _____________________________________...

Page 27: ......

Page 28: ...TECHNICAL PUBLICATIONS 4000 SRM 764 1 12 2 01 9 00 6 99 Printed in U S A...

Page 29: ......

Reviews: