6. Start-up
Warning:
The system may only be started-up by qualified staff.
»
Close shut-off valve(s) of soft water outlet
»
Make fused mains connection close to installation loca-
tion
»
Be aware that electrical connection must not be inter-
rupted at any time (do not use branch circuits intended
for lighting)
Warning:
Do not yet fill any salt into the brine tank. This may
only be made after start-up, since otherwise water level in the
brine tank cannot be set correctly.
Warning:
In order not to allow any (possibly contaminated)
water from the softener device enter the house water installation
before the first forced regeneration was run, the shut-off valve
towards house installation must be initially kept closed. In a next
step, forced regeneration should be carried out in order to drain
the water fed trough the softener device directly to the canal.
6.1 Operating the control valve for the first
time
Following the plugging-in of the power adapter, the time of day
display on the control valve will flash. Before executing any other
steps the system clock may be set.
Setting the clock
»
Press the
SET CLOCK
key („SET TIME“ will be dis-
played and the hour digits will flash)
»
Change the value shown using the
Δ
and
∇
arrow keys
»
Press the
NEXT
key for saving and advancing to minu-
tes‘ input (digits will flash)
»
Change the value shown using the
Δ
and
∇
arrow keys
»
Press the
SET CLOCK
key again in order to finish clock
setting; when done so, the display will show „TIME“