11  Monthly maintenance  

  Check the spaces between the equipment and the ground (clearance and 

height of fall). 

  Check  the  ground  surface  in  the  area  with  fall  protection  for  hard  objects 

and loose foundations. 

  Check all connecting elements and fittings for wear and tear and tighten if 

necessary. Replace damaged or missing parts. 

  Check  that  moving  metal  parts  (joints,  springs,  etc.)  move  smoothly  and 

are not worn. Replace if necessary. It is not necessary to lubricate joints as 
we only use maintenance-free metal roller bearings. 

  Check  all  attachments  such  as  chains,  ropes,  nets,  etc.  for  damage  and 

replace if necessary. 

  Check rubber parts, sleeves, etc. for wear and tear or damage and replace 

if necessary. 

  If necessary, remove excess padding material from the post footings due to 

danger of rotting. 

  Check the surface of wooden parts for damage caused by the weather or 

external influences and mould. Repair or replace if necessary. 

  Check  the  surface  of  plastic  and  metal  parts,  e.g.  slides,  for  damage  and 

replace if necessary. 

 

12  Quarterly maintenance  

  Detailed  inspection  of  the  operation  and  stability  of  the  equipment  paying 

particular attention to any wear and tear. 

  Tighten all forms of attachment. 

  Repaint and retreat surfaces. 

  Maintenance of fall protection surfaces. 

  Lubrication of joints. 

  Check the height of the fall and top up with loose filler if necessary. If the 

posts are labelled, top up as far as the mark. 

  Retighten all bolts 

 

Summary of Contents for 4652

Page 1: ...ik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc 1 A Assembly instructions Bird s nest tree E...

Page 2: ...CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc Revision history Revision 0 2006 02 13 The first allowed version Assembly instruction Revision 20 2019 09 13 Einschra...

Page 3: ...ist with part numbers 8 4 Abbreviations 12 5 Assembly instructions 14 6 Post installation checks 27 B Maintenance instructions Bird s nest tree EU GSM Art 4652 29 7 Introduction Maintenance 31 8 Gener...

Page 4: ...at may be required can be obtained directly from your supplier Please do not hesitate to call your supplier if you have any problems during installation or in case of any other questions Following ins...

Page 5: ...s of the complete item We reserve the right to change technical details of our articles which are serving for the further development of our articles and are reasonable for the customer Measurement to...

Page 6: ...her ground materials As recommended by manufacturer 3 Name and overall dimension of the largest component Steel post 1 item length 6 20 m 193 7 mm 4 Name and weight of the heaviest component 1 pallet...

Page 7: ...ger diameter of 63 mm grain size Soil class 5 ground with soil class 3 and 4 with big portion of stones portion 30 with bigger diameter of 63 mm grain size In case of sandy and soft soils the surface...

Page 8: ...9 1 mm 1240 mm 04 8 Glue laminated beam 139 mm 1650 mm lg 05 4 Top rope for glulam pole pre assembled on Pos 03 1850 mm lg 06 1 Flag blue threaded bolt 2x nuts M16 101 20 Bow shackle M8 VA 102 20 Grou...

Page 9: ...hnik huck net www huck net CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc 9 3 2 In symbols Table 3 2 Delivery contents in symbols Pos Quantity Symbol 01 1 193 7 mm...

Page 10: ...chnik huck net www huck net 10 CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc 05 4 1850 mm lg pre assembled on Pos 03 06 1 M16 101 20 M8 102 20 365 mm lg 103 17 M12...

Page 11: ...chnik huck net www huck net CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc 11 107 8 M10 x 175 mm 108 2 3 ml 109 8 M12 x 25 mm 112 1 500mm x 500mm Ring nut M16 pre a...

Page 12: ...fter mounting the steel post and the glue laminated beams the ropes must first be hooked in O K Top edge play level O K F Top edge foundation OAZ The opening must be show outwards not in tensile direc...

Page 13: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc 13...

Page 14: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net 14 CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc 5 Assembly instructions...

Page 15: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc 15...

Page 16: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net 16 CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc...

Page 17: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc 17...

Page 18: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net 18 CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc...

Page 19: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc 19...

Page 20: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net 20 CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc...

Page 21: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc 21...

Page 22: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net 22 CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc...

Page 23: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc 23...

Page 24: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net 24 CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc...

Page 25: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc 25...

Page 26: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net 26 CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc...

Page 27: ...ly in the following cases Safe equipment installation is not complete The protective surface has not been installed yet Appropriate maintenance work cannot guarantee operational safety 6 3 Removal of...

Page 28: ......

Page 29: ...GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc 29 B Maintenance instructions Bird s nest tree...

Page 30: ...30 CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc Revision history Revision 0 2006 02 13 The first allowed version Maintenance instruction Revision 19 2019 02 11 E...

Page 31: ...6 7 guidelines Please note Providing any necessary repairs are carried out a piece of play equipment that is inspected regularly cannot become so damaged that it is dangerous Any spare parts which may...

Page 32: ...olled cold welding may occur when the nuts are tightened To prevent this it is necessary to spray the nuts and bolts with Teflon spray or another similar lubricant 8 4 Spare parts All spare parts must...

Page 33: ...be tightened and checks carried out to ensure that there are no missing screws e g look out for holes you can see through 8 12 Preventing equipment use Use of the equipment should be prevented in the...

Page 34: ...pment 9 1 2 Maintenance intervals in the event of intensive use Please note that more frequent inspections and or maintenance are required if the play equipment is subject to intensive use 9 1 3 Fault...

Page 35: ...Huck Seiltechnik GmbH 35614 A lar Berghausen Germany seiltechnik huck net www huck net CAD1 Standard 4652 Montageanleitung Vogelnestbaum_Leimbinder_4652_SO_B_L_1_GBR doc 35 10 Regular maintenance...

Page 36: ...mage and replace if necessary X 7 Check the surface of wooden parts for damage caused by the weather or external influences and repair Paint with glaze or replace if necessary X 8 Check the surface of...

Page 37: ...eck all attachments such as chains ropes nets etc for damage and replace if necessary Check rubber parts sleeves etc for wear and tear or damage and replace if necessary If necessary remove excess pad...

Page 38: ...added or replaced Annual Maintenance 14 Annual maintenance Ascertaining that the equipment foundations and surfaces are safe for operation In particular the equipment should be checked for decay and...

Page 39: ...______________________________________________________________________________ Customer or operator _____________________________________________________________________________ Town Town council Kind...

Page 40: ......

Page 41: ...________________________________________________________________ Competent person in charge ___________________________________________________________________ ________________________________________...

Reviews: