UPS5000-E-(350 kVA-800 kVA)
User Manual (50 kVA Power Modules)
3 Installation
Issue 05 (2018-01-08)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
116
Figure 3-68
Routing signal cables from the top of the cabinet
The number and colors of signal cables in
----End
Follow-up Procedure
After connecting cables, reinstall the covers of the power distribution subrack, rear panel,
and side panel of the bypass cabinet.
After connecting cables, check that a certain clearance is reserved between the internal
switch (if any) extension pole and power cables to avoid friction.
3.2.6.2 Bottom Cable Routing
Context