Figure 5-9 Installing the server
3. When the two mounting ears of the server come into contact with the
mounting bars on the cabinet, tighten their captive screws to secure the
server. See (2) in
Step 3 Connect the power cables, network cables, VGA cable, and USB device as required,
and power on the server.
----End
5.7.3 Installing with Holding Rails
The holding rails are for a cabinet with a distance of 610 mm to 914 mm (24.02
in. to 35.98 in.) between the front and rear mounting bars.
When installed on holding rails, the servers cannot be stacked on each other in a
cabinet with a depth of 1 m (3.28 ft.).
If holding rails are used and the cable management arm (CMA) is equipped, the
server cannot be installed in a cabinet with a depth of 1 m (3.28 ft.).
Step 1 Install the holding rails.
1. Hold down the ejector release button on the front end of a holding rail and
pull out the hook. See (1) and (2) in
.
TaiShan 200 Server
User Guide (Model 2280)
5 Install and Configure
Issue 04 (2020-01-16)
Copyright © Huawei Technologies Co., Ltd.