5
Verifying the Installation
1. The inverter is installed correctly and securely.
Yes
▢
No
▢
N/A
▢
2. The DC switches and downstream AC output switch are OFF.
Yes
▢
No
▢
N/A
▢
3. Ground cables are connected correctly and securely, without open circuits
or short circuits.
Yes
▢
No
▢
N/A
▢
4. AC output power cables are connected correctly and securely, without open
circuits or short circuits.
Yes
▢
No
▢
N/A
▢
5. DC input power cables are connected correctly and securely, without open
circuits or short circuits.
Yes
▢
No
▢
N/A
▢
6. The communications cables are connected correctly and securely.
Yes
▢
No
▢
N/A
▢
7. All used connectors at the chassis bottom are applied with firestop putty.
Yes
▢
No
▢
N/A
▢
8. The AC terminal block is reinstalled.
Yes
▢
No
▢
N/A
▢
9. The maintenance compartment door is closed and the door screws are
tightened.
Yes
▢
No
▢
N/A
▢
10.The idle DC input terminals are sealed.
Yes
▢
No
▢
N/A
▢
11.The idle USB port is plugged with a waterproof plug.
Yes
▢
No
▢
N/A
▢
12.Idle AC OUTPUT and COM connectors are plugged and the locking caps
are tightened.
Yes
▢
No
▢
N/A
▢
6
Powering On the System
1. Turn on the AC switch between the inverter and the power grid.
2. Ensure that the DC switches at the inverter bottom are ON.
3. (Optional) Measure the temperatures at the joints between the DC terminals and the connectors
using a point-test thermometer.
Before turning on the AC switch between the inverter and the power grid, use a multimeter to check
that the AC voltage is within the specified range.
4. Observe the indicators to check the inverter operating status.
To check that the DC terminals are in good contact, check that the temperatures at the joints
between DC terminals and connectors do not exceed 85
°
C after the inverter has been running for
a period of time.
NOTE
NOTICE
14