Figure 1-1
Example network of device deployment in the scenario with the NMS
Router
OLT
Splitter
ONU_B
ONU_A
ONU_D
ONU_C
NMS client_B
NMS client_A
NMS
Splitter
MGC
The procedure for deploying network devices in the scenario with the NMS is as follows:
1.
According to the user's FTTx data plan, the commissioning engineer prepares the network
planning sheet and obtains the resource deployment sheet.
2.
The commissioning engineer imports the resource deployment sheet through the NMS to
implement the predeployment for the ONU.
3.
The hardware installation engineer draws the ONUs and sends them to the destination sites,
and then performs hardware installation, wiring, and power-on operations at the destination
sites.
4.
The hardware installation engineer checks the running status of the ONU that is installed
and powered on.
There are two LEDs, namely Link and Auth, on the ONU.
l
If the Link LED is on, it indicates that the upstream optical path is through.
l
If the Auth LED is blinking, it indicates that the ONU is registering.
SmartAX MA5616 Multi-service Access Module
Configuration Guide
1 Deploying Network Devices
Issue 04 (2011-10-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
4