References for Installation

Loading Configuration Data and Measuring the RSL

WLAN module

Web LCT

Open the maintenance compartment.

Load configuration data.

Close the maintenance compartment.

RSL tester

Measure the RSL.

If the RSL is lower than the required value, re-align the
RTN 360 pair.

Verifying the Installation

1

2

3

4

5

6

7

8

9

22/23 >>

Verify that RTN 360s are installed in planned locations and sufficient space is reserved
for maintenance.

Verify that the RTN 360s are securely installed. Attempt to gently turn the boxes
vertically and horizontally. If the RTN 360s do not move, they are securely installed.

Verify that OT terminals of PGND cables are tightly crimped and PGND cables are not
damaged or broken.

Verify that PGND cables are bound separately from other cables.

Verify that the protection ground of an RTN 360 shares the same ground bar with the
lightning protection ground of the building bearing the RTN 360.

Verify that shielded RJ45 connectors of outdoor network cables are intact and tightly
crimped and the cables are not damaged or broken.

Verify that PG covers are tightly screwed onto the network ports of RTN 360s, unused
ports are protected with caps, and removed caps are retained for future use.

Verify that outdoor network cables are routed along planned paths and bound properly
and neatly at equal intervals (about 1 meter), and the excess of each cable tie is cut off
without leaving sharp edges.

Verify that alignment scopes are removed and securely stored.

If a WLAN module is installed at the USB port, you can determine whether the WLAN module is working properly
by enabling it to search for the SSID of an NE in the wireless LAN. If the SSID can be searched out, the WLAN
module is working properly. If the SSID cannot be searched out, open the maintenance compartment and view
the WLAN module indicator. If the indicator is steady red, replace the WLAN module.

Summary of Contents for RTN 360 V100

Page 1: ... huawei com Copyright Huawei Technologies Co Ltd 2018 All rights reserved No part of this document may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co Ltd Huawei Technologies Co Ltd HUAWEI TECHNOLOGIES CO LTD RTN 360 V100 Quick Installation Guide Issue 07 Date 2018 10 30 ...

Page 2: ...tective gloves when handling the RTN 360 A high temperature warning label is attached to each RTN 360 Corrosion Anti corrosion measures are required if an RTN 360 is installed in a location that is prone to corrosion Contact the local Huawei office for details A location is prone to corrosion if it is Within 3 7 km of an ocean or a salt water lake Within 3 km of a heavy pollution source such as a ...

Page 3: ...sh drive may differ from that shown here E Alignment scope 1 Holes for mounting to a wall or pole four holes 2 3 4 5 6 Adjustment locking screw Elevation adjustment wing nut RTN 360 mounting bracket Adjustment locking screw Azimuth adjustment wing nut 4 Front view Interior of the maintenance compartment 1 2 3 6 5 C Hose clamp installation fasten the extra portion of the hose clamps onto the pole u...

Page 4: ...les are straight through cables Outdoor network cable Crimp the RJ45 connector Pin assignments of an RJ45 connector Before crimping ensure that the core wires are fully inserted in the RJ45 connector Pin No 1 2 3 4 5 6 7 8 Signal BIDA BGND BIDA BGND BIDB 48V BIDC BGND BIDC BGND BIDB 48V BIDD 48V BIDD 48V Function Bidirectional data wire A Power ground Bidirectional data wire A Power ground Bidirec...

Page 5: ...nd the length of an exposed cable L1 Cross sectional L1 mm Area of C mm2 1 7 1 5 7 7 8 9 11 13 14 16 16 Crimp the OT terminal lug Preparing an RSSI Test Cable Terminate one end of an outdoor network cable with an RJ45 connector by following instructions in Terminating an Outdoor Network Cable with Shielded RJ45 Connectors Blue core wire White and brown core wire Strip the other end of the cable re...

Page 6: ...l In this example port GE e is not used In practice determine whether to use this port based on your service plan In this example the RTN 360 uses port P E to receive services and power Wireless equipment at the opposite end 6 Align the RTN 360 with its peer 1 Install an RTN 360 on a pole or wall Connect one end of an outdoor network cable to port P E on the RTN 360 and lay out the cable Power ove...

Page 7: ...er ethernet supports a maximum distance of 100 meters 7 Align each RTN 360 with its peer 1 Install an RTN 360 on a pole or wall Connect an outdoor network cable to port P E on each RTN 360 and lay out the cable 2 3 Install the ground cable Receives GE service signals Receives only power signals Receives both GE service signals and power signals 4 Use an outdoor network cable to connect GE ports on...

Page 8: ...sher and a nut on each expansion bolt and then tighten 1 2 3 4 M6x60 bolt Nut Spring washer Flat washer 5 Expansion sleeve the nuts 1 Fastener 2 RTN 360 Drill holes and install expansion bolts at the locating points Install the RTN 360 box securely on the fastener Pass the hose clamps through the fastener and use the screws provided to secure the hose clamps onto a pole This side up Before securin...

Page 9: ... clamps to bind cables properly and neatly at intervals of about 1 meter and cut off the excess of each cable tie without leaving sharp edges ensuring a slack of about 5 mm Requirements for laying out PGND cables Connect PGND cables of devices at the same site to the same ground bar Do not route PGND cables overhead in outdoor scenarios Bind PGND cables separately from outdoor network cables and l...

Page 10: ...ng nuts 3 and 4 to adjust the azimuth and Align the peer RTN 360 with the local RTN 360 in the same way Remove the alignment scope gently to ensure that the aligned antennas are not affected 18 19 with its peer loosen the hose clamp re position the RTN 360 and then re fasten the hose clamp When mounting an RTN 360 to a wall use a 33 85 hex key with a standard length defined by ISO 2936 to tighten ...

Page 11: ...cable and the PI power cable are installed DIP switches are set correctly and the DIP switch for setting the power over ethernet mode for the used P E port is turned to the PSE PD side After setting the DIP switches switch off the power supply After waiting for 6 seconds switch on the power supply again Power on the equipment within 24 hours of unpacking During maintenance the power off time of th...

Page 12: ...ound bar with the lightning protection ground of the building bearing the RTN 360 Verify that shielded RJ45 connectors of outdoor network cables are intact and tightly crimped and the cables are not damaged or broken Verify that PG covers are tightly screwed onto the network ports of RTN 360s unused ports are protected with caps and removed caps are retained for future use Verify that outdoor netw...

Page 13: ...References for Installation 24 25 ...