The PLC CCO must be installed in a well-ventilated environment to ensure good heat
dissipation.
Carrier Requirements
The carrier where the PLC CCO is installed must be fireproof.
Do not install the PLC CCO on flammable building materials.
Ensure that the surface on which the PLC CCO is to be installed is strong enough.
Installation Dimensions
Figure 3-1
shows the PLC CCO installation dimensions.
Figure 3-1
Installation dimensions (unit: mm)
(1) Guide rail mounting hole
(2) Ear mounting hole
Installation Space Requirements
Reserve clearance around the PLC CCO to ensure sufficient space for installation and
maintenance.