6 Installing Cable Troughs
Issue 02 (2015-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
93
6
Installing Cable Troughs
This section describes how to install cable troughs.
6.1 Installing 600 mm Wide Cable Troughs
Context
Install two 600 mm wide cable troughs on the top of each server cabinet, PDU8000, and
integrated cabling cabinet. When installing cable troughs, first install two cable troughs on the
top of the PDU8000, and then install the other cable troughs on the top of other cabinets along
the aisle containment in sequence.
shows the 600 mm wide cable trough. The BOM number of 600 mm wide cable
trough is 21500551.
Figure 6-1
600 mm wide cable trough
(1) Partition
(2) Bracket
(3) Pallet
(4) Side panel
When installing a cable trough, be aware of the route for the PDU2000 cables and industrial
connectors on top of a cabinet:
Cold aisle containment: First install a cable trough close to the front door of the cabinet.
When installing a cable trough close to the rear door, move the cables that have been laid