FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
14 Power-On Commissioning
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
196
Device
Reference
or you can click
Precision PDC
PDU8000 Modular Precision PDC Quick
Guide (1100 mm Deep)
The document is delivered with the device,
or you can click
14.3 Commissioning the Power Supply and Distribution
System (New Main Way)
Commission the power-on new main way by referring to the documents delivered with it.
14.4 Commissioning the Cooling System
If the smart module is located in a humid environment and condensation appears outside the
doors of the cold aisle containment, lower the discharge air temperature of the air conditioner
or dehumidify the room.
To commission a cooling device, follow instructions in the documents delivered with it.
lists the reference documents.
Set the initial temperature to 20ºC and relative humidity to 50% for air conditioners. To adjust the
temperature for air conditioners, follow instructions provided in the documents delivered with the air
conditioners.
Table 14-2
Reference documents for the cooling system
Device Name
Reference
NetCol5000-C 30 kW
Chilled Water In-Row
Precision Air
Conditioner
NetCol5000-C 30 kW Chilled Water In-Row Precision Air
Conditioner Quick Guide (Simplified Edition)
The document is delivered with the device, or you can click