14 Power-On Commissioning
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
195
14
Power-On Commissioning
14.1 Power-On Commissioning Process
shows the power-on commissioning process.
Figure 14-1
Power-on commissioning process
14.2 Commissioning the Power Supply and Distribution
System (Power Supply and Distribution Cabinet)
For details about how to commission each device in the power supply and distribution system,
see the documents delivered with it.
lists the reference documents.
Table 14-1
Device
Reference
Integrated UPS
UPS5000-E-(40 kVA–128 kVA) Quick
Guide (Integrated UPS 2.0)
The document is delivered with the device,