Installation Sequence
Subcategory
Item
Corresponding Chapter in Installation Guide
Diagram ID
Diagram Name
Installing Pre-fab. Module Bases
Installing Pre-fab. Module Bases
Removing the Pre-fab. Module Cover Removing the Pre-fab. Module Cover
Hoisting and Securing Pre-fab.
Modules
Hoisting and Securing Pre-fab. Modules
Grounding Pre-fab. Modules
Grounding Pre-fab. Modules
Grounding Pre-fab. Modules
NO.S003
Pre-fab. Module Grounding Position Diagram
Installing the External Cable Tray
Installing the External Cable Tray
(Optional) Installing the External Cable Tray
NO.S005
External Cable Tray Installation Position Diagram
Installing a Fire Hammer
Installing a Fire Hammer
Installing a Fire Hammer
NO.S006
Fire Hammer Installation Position Diagram
Installing Awnings
Installing Awnings
(Optional) Installing Awnings
NO.S007
FIG rain eave mounting position
Installing Drainpipes
Installing Drainpipes
Installing Water Refill Pipes
Installing Water Refill Pipes
Containers external cable installation Containers external cable installation
N/A
NO.C004
Air conditioning unit communications cable port schematic
Installing ECC800 Accessories
(Optional) Installing ECC800 accessories
NO.M004
Monitoring Device Installation Position Diagram
Installing the WiFi Antenna
Installing the WiFi antenna
NO.M004
Monitoring Device Installation Position Diagram
Installing a Pad
Installing a Pad
NO.M004
Monitoring Device Installation Position Diagram
(Optional) Installing the Fire Cylinder (CE)
Installing Batteries for the Extinguishant
Control Panel (CE)
Connecting External Cables
Installing External Input Power
Cables
Installing External Input Power
Cables
Installing External Input Power Cables
NO.P008
Wiring Diagram from the Mains to the Power PDB
Installing Power Supply and
Distribution Devices
Battery Wiring Diagram
Installing Batteries
Installing Batteries
NO.P009
Battery Wiring Diagram
Installing Pre-fab. Modules
Installing External Accessories
for Pre-fab. Modules
Installing Devices Inside Pre-
fab. Modules
Installing External Air
Conditioner Pipes
Installing CE-Certified Fire
Extinguishing Devices
Fire Extinguishing Device Installation Position Diagram (CE)
Site Space and Pre-fab. Module Installation Position Diagram (Single-capacity
Base Scenario)
Pre-fab. Module Pipe Installation Position Diagram
NO.S002
NO.S004
NO.F004
Checklist of Devices Installed Onsite
Installing Monitoring Devices
Installing Fire Extinguishing
Devices
Installing an External Horn Strobe (CE)
Installing Pre-fab. Modules (Base
Solution)
Installing External Air Conditioner
Pipes
Summary of Contents for FusionModule1000A40 ICT Solution
Page 11: ...NO S003 Pre fab Module Grounding Position Diagram ...
Page 12: ...NO S005 External Cable Tray Installation Position Diagram ...
Page 13: ...NO S006 Fire Hammer Installation Position Diagram ...
Page 14: ...NO S007 FIG rain eave mounting position ...
Page 15: ...Pipe window NO S004 Pre fab Module Pipe Installation Position Diagram ...