PDC-(0250, 0400, 0630) DC0384BXA Battery Circuit
Breaker Box
Quick Installation Guide
3 Installation
Issue 03 (2019-05-20)
Copyright © Huawei Technologies Co., Ltd.
12
Figure 3-3
Installing expansion bolts (unit: mm)
Data provided in this figure is for reference only. Determine the data based on actual situations.
Step 4
Align the four cucurbit holes in the BCB box with the bolts mentioned. Then move the BCB
box downwards until the screws fit into the mounting holes.
Step 5
Secure the four bolts, the BCB box is secured to the wall.
Step 6
If there are multiple BCB boxes, secure the other BCB boxes to the wall.
----End
Rack-mounted
Step 1
Install four mounting brackets on the BCB box using eight M4 screws.
Step 2
Install screws on a battery rack (partially tighten the screws), mount the BCB box onto the
screws, and tighten the screws.