DBS3900 LampSite
Installation Guide
7 Installing a pRRU3901
Issue 08 (2016-05-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
80
Figure 7-16
Installing a pRRU3901 on a pole
----End
7.4.5 Installing a pRRU3901 on a Plate
This section describes how to install a pRRU3901 on a plate. If a suspended ceiling plate has
adequate load bearing capacity and installation space, the pRRU3901 can be installed on the
plate. However, it is good practice not to install a pRRU3901 on an aluminum plate.
Procedure
Step 1
Determine the position for installing the pRRU3901 based on the construction blueprint and
the clearance requirements.
For details about the clearance requirements, see 7.1.3 Space Requirements.
Step 2
Place the mounting bracket in the installation position against the wall. Then, level the
mounting bracket and use a marker to mark two anchor points. See Figure 7-17.