17
Verifying the Installation
5.2
5
Verifying the Installation
No.
Acceptance Criterion
1
The battery is installed correctly and securely.
2
The cables are routed properly as required by the customer.
3
Cable ties are secured evenly and no burr exists.
4
The ground cable is connected correctly and securely.
5
The battery switch and all switches connected to the battery are OFF.
6
The DC input power cables and signal cables are connected correctly and securely.
7
Idle terminals and ports are locked by watertight caps.
8
The installation space is proper, and the installation environment is clean and tidy.
After electrical connections are complete, check that cables are correctly and securely connected,
install the external protective cover, and secure it using screws.
Installing the Cover
5.1