Install the SSD module on the M.2 SSD enablement board:
a. Insert the SSD module into the SSD slot at a 45 degree angle, and then gently press it down against the M.2 SSD
Enablement board.
b. Secure the SSD module to the M.2 SSD enablement board with a screw.
c. To install a second SSD module, repeat the process.
10. Install the M.2 SSD enablement board.
14. Install the server into the rack.
15. Connect all peripheral cables to the server.
16. Connect each power cord to the server.
17. Connect each power cord to the power source.
19. If removed, install the bezel.
The installation is complete.
ODD options
Installing the ODD in LFF
Prerequisites
Before you perform this procedure, make sure that you have a T-10 Torx screwdriver available.
92
Hardware options installation
Summary of Contents for ProLiant DL325 Gen10 Plus
Page 36: ...10 Remove the inner drive cage blank 11 Remove the fan wall covers 36 Operations...
Page 37: ...12 For SFF drive cage remove the cable covers 13 Remove the drive cage latches Operations 37...
Page 38: ...14 Remove the outer drive cage LFF SFF 38 Operations...
Page 52: ...52 Operations...
Page 67: ...3 Remove the drive blank LFF SFF 4 Prepare the drive LFF Hardware options installation 67...
Page 119: ...SFF Cable routing Front I O LFF Cabling 119...
Page 120: ...SFF Cable routing Serial port 120 Cabling...