Chapter 2
Installing the HP-HSC ATM/155 Adapter
Verifying Hardware Installation
Verifying Hardware Installation
To verify that you have correctly installed the HP-HSC ATM/155
adapter, follow these steps:
Step 1. Look at the Carrier LED on the ATM adapter. A green light means that
the hardware installation was successful and that the ATM cables are
correctly connected.
Step 2. If the LED is not green, do the following things:
a. Ensure that the system and the ATM switch are powered on.
b. Swap (with each other) the transmit and receive cables connected to
the ATM adapter.
Step 3. If the LED is still not green, see the ATM Configuration and
Troubleshooting Guide for troubleshooting information.