7.
Slide the neutralisation box (6, Fig. 27) into the boiler
until the hose of the siphon (5a, Fig. 26) is directly
beneath the drain connection.
6
Fig. 27
8. The hose of the siphon (5a, Fig. 26) can be easily
pushed onto the drain connection of the condensate
drip tray by lifting the neutralisation box (7, Fig. 28).
7
Fig. 28
9. Slightly loosen the jubilee clip (8, Fig. 29) and push
it upwards. Firmly tighten the jubilee clip (connection
must be sealed).
8
Fig. 29
10.
Fill the neutralisation box with water.
11.
Fit the front cover (9, Fig. 30) of the neutralisation
box.
12.
Fit base plate (3, Fig. 25) and front cover (2a).
9
Fig. 30
Before commissioning the neutralisation
box must be filled with water in order to
prevent flue gas leakage.
The condensate drain must be made
of corrosion-resistant material.
13
4 213 784 / 00
ASSEMBLY
Summary of Contents for 41-UltraOil 16