ASSEMBLY INSTRUCTION
1). Install the Rear Stabilizer
Attach the Rear stabilizer (2) to the Main frame (1) with two sets of
M8×20 Bolts (38), Φ8 spring
washers (51), and
Φ8 Flat washers (50).
(Refer figure 1)
2). Install the Front Stabilizer
Attach the Front stabilizer (13) to the Main Frame (1) with
two sets of
M8×20 Bolts (38), Φ8 spring washers (51),
and
Φ8 Flat washers (50). (Refer figure 2)
3). Install the Front Upright Frame
a. On the lower position of the front upright frame (14), there is the tension control
(21).Connect the joint of the tension control (21) with the tension control wire (12) firmly. <
Note: at first, please turn the tension control
’s knob to the bottom of the “-“ direction (in this
situation, the joint of the tension control will be extended to the longest)>. Then put the end
of resistance cable into the spring hook of Tension control wire (12) as shown on drawing
A
of figure 3.
Pull the resistance cable up and force it into the gap of metal bracket of Tension control wire
(12) as shown on drawing
B
of figure3
Connect the resistance cable with the Tension control wire (12) completed as shown on
drawing
C
of figure 3. If the upper side of the tension control wire cannot fix perfectly in the
gap of metal bracket, please adjust the nut which below the bracket to the suitable position.
Summary of Contents for H9249 Series
Page 1: ...INSTRUKCJA U YTKOWANIA MANUAL INSTRUCTION N VOD K OBSLUZE...
Page 5: ...NARZ DZIA...
Page 18: ...TOOLS...
Page 29: ...N AD...
Page 37: ......