To line up motor and fan pulleys: 

1.

 

Loosen setscrews from the fan pulley.  

2.

 

Slide the fan pulley down the axe and line up with the motor, using a ruler to make sure 
that it’s in parallel with the belt.  

3.

 

Tight the fan pulley using a tension adjuster crew.  

 
 
 

 

 
 
 
 

COMPRESSOR LUBRICANT 

 

-

 

Compressors  with  R410a  refrigerant  use  synthetic  polyester  oil,  each  manufacturer  using  a 
specific oil for his product.  

-

 

The system must not remain open to the atmosphere more than 15 minutes.  

-

 

Due to its hygroscopic qualities, you must be very careful during manipulation: when synthetic 
oils mix up with mineral oil, they deteriorate causing obstructions and even the breakdown of 
the compressor. Do not mix them under any circumstance.  

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 

WRONG ALIGNMENT 

90

°

 

WRONG 

WRONG 

90

°

 

RIGHT POSITION OF THE RULER 

90

°

 

Summary of Contents for CCHA

Page 1: ...HA ECHA CCHBA ECHBA Installation operation and maintenance instructions 1 Installation operation and maintenance instructions CCHA ECHA Cooling Only CCHBA ECHBA Heat Pump SPLIT HORIZONTAL UNITS AIR AI...

Page 2: ...allation operation and maintenance instructions 2 CONTENTS INTRODUCTION 3 SAFETY PRECAUTIONS 4 RECEPTION 5 LOCATION INSTALLATION 8 START UP 10 TECHNICAL DATA 14 DIMENSIONS 16 REFRIGERANT CHARGE 22 REG...

Page 3: ...e etc are potentially hazardous and must be kept out of reach of children Recycle packing materials in accordance with local legislation The units must be used only for the purpose for which they are...

Page 4: ...ation operation and maintenance instructions as well as the ones indicated in labels of the unit Do not forget to strictly follow any other safety codes Use safety glasses work gloves and any other sa...

Page 5: ...ccordance with local power supply In case of any flaw or anomaly detected please contact HITECSA RIGGING Before moving the unit make sure that all panels are well fixed Raise and set down the equipmen...

Page 6: ...um service area according to Fig 2 Choose a place free of dust or any other foreign material that could clog or damage the condenser coil The location should also be a place that cannot be flooded Con...

Page 7: ...d maintenance instructions 7 WEIGHT DISTRIBUTION Kg UNIT SETTLEMENT Make sure that the unit is correctly levelled The bed frame should be strong and solid enough to support the weight of the machine V...

Page 8: ...nted o Grilles air diffusers air ducts and flexible connections are in good condition o Electrical power source is in accordance with what is said in the nameplate o Fans rotate in the right direction...

Page 9: ...or circuit breaker MCB curve D 4 Main power switch 5 Indoor fan motor supply 400 3 or 230 1 6 Electric heating wiring option 7 Electric heating supply option de 400 3 or 230 1 8 Remote control OPERAT...

Page 10: ...17 17 17 Potencia total absorbida 3 kW 2 6 3 2 3 7 4 8 4 9 6 2 Corriente total absorbida 3 A 13 19 12 15 15 13 Potencia total absorbida 4 kW 3 4 4 3 4 8 5 8 6 5 8 5 Corriente total absorbida 4 A 15 19...

Page 11: ...mperatures below 0 C it is necessary to provide thermal insulation or electrical heating wire to avoid water freezing and tube damages It is advisable to install a trap with proper dimensions AIR DUCT...

Page 12: ...ley 5 Tensor adjustment screw 6 Setscrew 7 Mobile flap 8 Fix flap 7 6 8 3 1 5 4 2 Polea Pulley abiertas Fijo Variable Correa kW A CCHBA 751 X 1 5 3 6 150 E25 1A 75 100 E 24 1A A 45 0 CCHBA 801 X 1 5 3...

Page 13: ...r crew COMPRESSOR LUBRICANT Compressors with R410a refrigerant use synthetic polyester oil each manufacturer using a specific oil for his product The system must not remain open to the atmosphere more...

Page 14: ...tro tubos 3 8 3 8 3 8 3 8 3 8 3 8 VENTILADOR INTERIOR Tipo Modelo 9 7 DD 9 9 DD 10 10 DD 10 10 DD 10 10 DD 10 10 SS Potencia motor kW 0 120 0 250 0 250 0 373 0 373 0 550 Voltaje V 230 1 230 1 230 1 23...

Page 15: ...3 8 3 8 VENTILADOR INTERIOR Tipo Modelo 12 9 SS 12 9 SS 12 9 SS 12 9 SS 12 12 SS 15 15 SS Potencia motor kW 0 735 0 735 0 735 0 735 1 500 2 200 Voltaje V 400 3 400 3 400 3 400 3 400 3 400 3 Corriente...

Page 16: ...CCHA ECHA CCHBA ECHBA Installation operation and maintenance instructions 16 DIMENSIONS CCHA CCHBA 351 ECHA ECHBA 351...

Page 17: ...CCHA ECHA CCHBA ECHBA Installation operation and maintenance instructions 17 CCHA CCHBA 371 401 501 ECHA ECHBA 371 401 501...

Page 18: ...CCHA ECHA CCHBA ECHBA Installation operation and maintenance instructions 18 CCHA CCHBA 701 721 751 801 ECHA ECHBA 701 721 751 801...

Page 19: ...ne Circulation speed of the refrigerant Refrigerant mass DISCHARGE LINE In heat pump operation the gas line works as discharge line WARNING When working with the machines in operation discharge line t...

Page 20: ...oor unit L NEA DE GAS L NEA DE L QUIDO A B A UNIDAD INTERIOR B UNIDAD EXTERIOR L NEA DE GAS L NEA DE L QUIDO L NEA DE GAS L NEA DE L QUIDO L NEA DE L QUIDO A B A UNIDAD INTERIOR B UNIDAD EXTERIOR A B...

Page 21: ...ll be insulated only when exposed to high temperatures solar radiation etc Horizontal segment of suction line 4 pitch towards the compressor In addition to refrigerant sometimes it s necessary to add...

Page 22: ...e and quick evaporation refrigerant R410A cannot be kept in liquid phase inside charge cylinder because bubbles would form making reading difficult WARNING If it s necessary to make welding operations...

Page 23: ...every 1 000 hours Fan and motors do not need additional lubrication Drainage system verify condition and good operation of the drainage tray Make sure that holes at the base of the unit are not block...

Page 24: ...A Installation operation and maintenance instructions 24 www hitecsa com HIPLUS AIRE ACONDICIONADO S L Masia Torrents 2 08800 Vilanova i la Geltr Barcelona Espa a Tel 34 93 893 49 12 Fax 34 93 893 96...

Reviews: